You can install and mount the charging station to the ground with 2 available solutions. By prepar-
ing the concrete/anshor plate and second option is to position the charger over the ready concrete
(cabling should be ready before).
3.4 - INSTALLING THE STATION BY PREPARING THE CONCRETE AND ANCHOR
PLATE
Make sure that the materials used for the concrete foundation and the installation procedures
follow local building regulations and safety standards.
For Preparing and Mounting the Anchor Plate, below three steps should be followed as also
shown in figures:
1-
Insert each nut to each bolt one by one as shown in figure.
2-
Insert the anchor plate to the bolts as shown in figure.
3-
Assemble the nuts over the anchor bolt to fix it with the bolts.
1
2
3
For Preparing Installation area and cabling, below steps should be followed as also shown in
figures:
1-
Dig a pit (dimensions 200x580x300 – DxWxH in mm) for anchor bolts and plate assembly. The
pit floor should be trampled and horizontal
2-
Place anchor assembly in the pit.
3-
Cables must be placed in the middle and should be pulled through the plate hole, before con-
crete applied. Pull the supply cable and possible data cable through the ground mounting box
cable gland(s) and further through the mounting box cable hole. For AC mains cable minimum
500 mm, for ethernet cable minimum 2 meters from the ground surface of the mounting box
should be left.
4-
Fill the pit with concrete. Then adjust the assembly as seen in the picture. 2nd bolt top surface
must be on the ground level. Level indicator ruler can be used while adjusting.
5-
Let the concrete solidify, make sure the surface stays solid and level during the process.
6-
Put the bottom part of the charging station over the anchor plate as shown in figure. Put in the
cables from the middle of the bottom cover.
7-
Assemble the metal holes and nuts over the bottom cover and fix it to the surface, as shown
in figure.