3.5 - INSTALLING THE STATION OVER THE READY CONCRETE SURFACE
(Where cabling is also ready)
For Preparing Installation area and cabling, below steps should be followed as also shown in
figures. Before this, please be sure that cables are placed in the middle and the cables should be
prepared before the installation. For AC mains cable minimum 500 mm, for ethernet cable mini-
mum 2 meters from the ground surface of the mounting box should be left.
1-
Open holes over the surface by using the bottom cover of the charging station as drilling
template and use the impact drill with metric10 drill pit as in dimensions shown in figure below.
(450mm x 76mm). You can use the bottom cover as template for marking the holes.
2-
Place bottom cover of the charger over the opened holes and assemble the steel expansion
bolts (10x80mm) which are supplied in package of the charging station, as shown figure below.
Use a hammer slightly to well position the bolts and then use the approprate spanner to tighten
the bolts.
3-
Position and mount the charging station over the bottom cover as shown in figure.
4-
Assemble 4 screws inside the charging station to the bottom cover with approptate allen wren-
ch as shown in figure below.
2
3
1