Once the photovoltaic system has been activated, check that:
The consumption value remains constant as the
photovoltaic power increases.
Note
: If the conditions described above are not met:
•
Check that the current sensor is positioned correctly and then proceed with
restarting the system.
* Check that the power of the loads in use does not change:
•
Heat pump or pump → Load variable over time
•
Light or hairdryer → Load constant over time
Hybrid Inverter
ON
GRID
OFF
ON
4) Switch on the photovoltaic system by turning the
DC circuit breaker to the ON position
Hybrid Inverter
ON
GRID
ON
1
2
Battery
ON
3
1
2
3
5) Switch on the battery(ies) checking that the
system is operating in the mode described in the
section
OPERATING STATUSES IN AUTOMATIC
MODE:
•
PV>Load →battery charging
•
PV<Load Battery discharging
•
PV=Load Battery on stand-by
NOTE
:
WeCo and Azzurro batteries will charge to 100% when
first started