![York YHAU-CGN Installation Operation & Maintenance Download Page 21](http://html1.mh-extra.com/html/york/yhau-cgn/yhau-cgn_installation-operation-and-maintenance_4203195021.webp)
FORM 155.32-ICOM2.EN.UL
SECTION 3 - HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
ISSUE DATE:1/10/2018
JOHNSON CONTROLS
21
SECTION 3 - HANDLING, STORAGE, INSTALLATION
AND REASSEMBLY
This chiller-heater is for air conditioning or a cooling manufacturing process. Transport,
store, and use this chiller-heater under the following conditions:
• Installation location: Indoor, non-explosion area
• Ambient temperature: 50~104 °F (10 ~ 40°C)
• Humidity: 10 ~ 90% (RH%)
• Altitude: 3333 Ft (1000 m) or lower
If the plant room will ever drop below 50 °F (10°C), you must install the cold ambient option.
INSPECTION
The unit must be inspected prior to customer use by a Johnson Controls Service
representative. All damage or possible damage must be reported to the transportation
company. For further details, see
.
INSPECTION WINDOW
The inspection window of the exhaust gas duct or chimney must not be turned to the aisle
side in case the exhaust gas duct or chimney has a problem from a unit failure or burner
combustion deterioration. If it must be turned to the aisle side, install a guard fence around
the inspection window.
DANGER: Rigging and lifting should only be done by a professional rigger in accor-
dance with a written plan. The most appropriate rigging and lifting method will depend
on job specific factors, such as the equipment available and site needs. Therefore, a
professional rigger must determine the rigging and lifting method to be used. It is be-
yond the scope of this manual to specify rigging and lifting details.
LD18119