FORM 201.10-NM1
41
YORK INTERNATIONAL
INSTALLATION
WARNING
To protect warranty, this equipment must be installed
and serviced by an authorized YORK service
mechanic or a qualified service person experienced in
chiller installation. Installation must comply with all
applicable codes, particularly in regard to electrical
wiring and other safety elements such as relief valves,
HP cut-out settings, design working pressures, and
ventilation requirements consistent with the amount
and type of refrigerant charge.
Lethal voltages exist within the control panel. Before
servicing, open and tag all disconnect switches.
INSTALLATION CHECK LIST
The following items, 1 thru 5, must be checked before
placing the units in operation.
1. Inspect the unit for shipping damage.
2. Rig unit per Fig. 6A or 6B. Remove unpainted shipping
braces.
3. Open the unit only to install water piping system. Do
not remove protective covers from water connections
until piping is ready for attachment. Check water
piping to insure cleanliness.
4. Pipe unit using good piping practice (see ASHRAE
handbook section 215 and 195 or YORK Service
Manuals for detailed piping).
5. Check to see that the unit is installed and operated
within LIMITATIONS.
The following pages outline detailed procedures to be
followed to install and start up the chiller.
HANDLING
These units are shipped as completely assembled units
containing full operating charge, and care should be taken
to avoid damage due to rough handling.
The units are shipped with export crating unless it is
specified by Sales Order.
A unit should be lifted by inserting hooks through the holes
provided in unit base rails. Spreader bars should be used
to avoid crushing the unit frame rails with the lifting
chains. (See Fig. 6A & 6B)
INSPECTION
Immediately upon receiving the unit, it should be
inspected for possible damage which may have occurred
during transit. If damage is evident, it should be noted in
the carrier’s freight bill. A written request for inspection by
the carrier’s agent should be made at once. See “Instruc-
tion” manual, Form 50.15-NM for more information and
details.
LOCATION AND CLEARANCES
These units are designed for outdoor installations on
ground level, rooftop, or beside a building. Location
should be selected for minimum sun exposure and to
insure adequate supply of fresh air for the condenser. The
units must be installed with sufficient clearances for air
entrance to the condenser coil, for air discharge away
from the condenser, and for servicing access.
In installations where winter operation is intended and
snow accumulations are expected, additional height must
be provided to insure normal condenser air flow. (See
DIMENSIONS.)
FIG. 6A – RIGGING THE CHILLER (2-MOD)
LD01096
FIG. 6B – RIGGING THE CHILLER (3-MOD)
LD01439
Summary of Contents for Millennium YCAS 216X
Page 11: ...FORM 201 10 NM1 11 YORK INTERNATIONAL YCAS 140 246 DIMENSIONS English LD01444 LD01446...
Page 13: ...FORM 201 10 NM1 13 YORK INTERNATIONAL YCAS 140 246 DIMENSIONS SI LD01440 LD01442...
Page 15: ...FORM 201 10 NM1 15 YORK INTERNATIONAL YCAS 216X 266X DIMENSIONS English LD01454 LD01454...
Page 17: ...FORM 201 10 NM1 17 YORK INTERNATIONAL YCAS 216X 266X DIMENSIONS SI LD01450 LD01448...
Page 33: ...FORM 201 10 NM1 33 YORK INTERNATIONAL 28514A FILTER DRYER LIQUID STOP VALVE...
Page 37: ...FORM 201 10 NM1 37 YORK INTERNATIONAL LD01285 FIG 3 SCREW CHILLER REFIGERANT FLOW DIAGRAM...
Page 59: ...FORM 201 10 NM1 59 YORK INTERNATIONAL FIG 11 CONTINUED LD01465 D...
Page 61: ...FORM 201 10 NM1 61 YORK INTERNATIONAL FIG 12 CONTINUED LD01458 D...
Page 69: ...FORM 201 10 NM1 69 YORK INTERNATIONAL FIG 16 CONTINUED LD01206 D...
Page 71: ...FORM 201 10 NM1 71 YORK INTERNATIONAL FIG 17 CONTINUED LD01202 D...