9. Check tightness of power wiring inside the power
panel on both sides of the motor contactors and
overloads.
θ
10. Check for proper size fuses in main and control
circuits, and verify overload setting corresponds
with RLA and FLA values in electrical tables.
θ
11. Assure 115 VAC Control Power to CTB2 has 15
AMP minimum capacity.
See Table 1, page 19.
θ
12. Be certain all water temp sensors are inserted
completely in their respective wells and are coated
with heat conductive compound.
θ
13. Assure that evaporator TXV bulbs are strapped
onto the suction lines at 4 or 8 o’clock positions.
PANEL CHECKS
(Power ON – Both Unit Switch OFF)
θ
1. Apply 3-phase power and verify its value. Volt-
age imbalance should be no more than 2% of the
average voltage.
θ
2. Apply 115 VAC and verify its value on the termi-
nal block in the Power Panel. Make the measure-
ment between terminals 5 and 2 of CTB2. The
voltage should be /- 10%.
JOB NAME: ______________________________
SALES ORDER #: _________________________
LOCATION: _______________________________
SOLD BY: ________________________________
INSTALLING
CONTRACTOR: ___________________________
START-UP
TECHNICIAN/
COMPANY: _______________________________
START-UP DATE : _________________________
CHILLER MODEL #: _______________________
SERIAL #: ________________________________
CHECKING THE SYSTEM
PRIOR TO INITIAL START (No Power)
Unit Checks
θ
1. Inspect the unit for shipping or installation
damage.
θ
2. Assure that all piping has been completed.
θ
3. Visually check for refrigerant piping leaks.
θ
4. Open suction line ball valve, discharge line ball
valve, and liquid line valve for each system.
θ
5. The compressor oil level should be maintained
so that an oil level is visible in the sight glass.
The oil level can only be tested when the com-
pressor is running in stabilized conditions, guar-
anteeing that there is no liquid refrigerant in the
lower shell of the compressor. In this case, the
oil must be between 1/2 and 3/4 in the sight glass.
At shutdown, the oil level can fall to the bottom
limit of the oil sight glass.
θ
6. Assure water pumps are on. Check and adjust
water pump flow rate and pressure drop across
the cooler (see LIMITATIONS). Verify flow switch
operation.
NOTE: Excessive flow may cause catastrophic
damage to the evaporator.
θ
7. Check the control panel to assure it is free of
foreign material (wires, metal chips, etc.).
θ
8. Visually inspect wiring (power and control). Wir-
ing MUST meet local codes. See Figures 2 - 5.
OPTIONS
Display Language
Sys 1 Switch
Sys 2 Switch
Unit Type
Chilled Liquid
Ambient Control
Local/ Remote Mode
Control Mode
Display Units
Lead/Lag Control
Fan Control
Manual Override
COOLING SETPOINTS
Cooling Setpoint
Range
EMS-PWM Max. Setpoint
PROGRAM
Discharge Pressure Cutout
Suct. Pressure Cutout
Low Amb. Temp. Cutout
Leaving Liquid Temp. Cutout
Anti-Recycle Time
Fan Control On-Pressure
Fan Differencial Off-Pressure
Total # of Compressors
TABLE 22
– SETPOINTS
Installation
Summary of Contents for MILLENNIUM YCAL0043SC
Page 106: ...YORK INTERNATIONAL 106 ELEMENTARY DIAGRAM YCAL0043SC YCAL0087SC FIG 11 ELEMENTARY DIAGRAM ...
Page 109: ...YORK INTERNATIONAL 109 FORM 150 62 NM2 This page intentionally left blank ...
Page 110: ...YORK INTERNATIONAL 110 ELEMENTARY DIAGRAM YCAL0107SC FIG 13 ELEMENTARY DIAGRAM ...
Page 112: ...YORK INTERNATIONAL 112 FIG 14 ELEMENTARY DIAGRAM ELEMENTARY DIAGRAM YCAL0107SC LD03534 ...
Page 113: ...YORK INTERNATIONAL 113 FORM 150 62 NM2 This page intentionally left blank ...
Page 114: ...YORK INTERNATIONAL 114 ELEMENTARY DIAGRAM YCAL0117SC YCAL0173SC FIG 15 ELEMENTARY DIAGRAM ...
Page 116: ...YORK INTERNATIONAL 116 ELEMENTARY DIAGRAM YCAL0117SC YCAL0173SC FIG 16 ELEMENTARY DIAGRAM ...
Page 118: ...YORK INTERNATIONAL 118 ELEMENTARY DIAGRAM YCAL0197SC YCAL0253SC FIG 17 ELEMENTARY DIAGRAM ...
Page 120: ...YORK INTERNATIONAL 120 ELEMENTARY DIAGRAM YCAL0197SC YCAL0253SC FIG 18 ELEMENTARY DIAGRAM ...
Page 129: ...YORK INTERNATIONAL 129 FORM 150 62 NM2 This page intentionally left blank ...
Page 130: ...YORK INTERNATIONAL 130 This page intentionally left blank ...
Page 131: ...YORK INTERNATIONAL 131 FORM 150 62 NM2 This page intentionally left blank ...