67
13.4.6 Re-Installation When the Outdoor
Unit Requires Repairs
1. Evacuation for
the whole system
Procedure:
1).Confirm that both the 2-way and 3-way
valves are open.
2). Connect the vacuum pump to 3-way valve’s
service port.
3). Conduct an evacuation for approximately
one hour. Confirm that the compound meter
displays a value of -0.1Mpa(14.5Psi).
4). Close the valve (Low side) on the charge set,
turn off the vacuum pump. After 5 minutes,
confirm that the gauge needle is not moving.
5). Disconnect the charge hose from the
vacuum pump.
2. Refrigerant charging
Procedure:
1). Connect the charge hose to the charging
cylinder. Open the 2-way 3-way valve.
With the charge hose you disconnected from
the vacuum pump, connect it to the valve at the
bottom of the cylinder. If the refrigerant is
R410A, place the cylinder bottom-up to ensure
liquid charge.
2). To purge the air from the charge hose, open
the valve at the bottom of the cylinder and press
the check valve on the charge set (be careful of
the liquid refrigerant).
3) Place the charging cylinder onto the
electronic scale and record the weight.
4). Open the valves (Low side) on the charge
set and charge the system with liquid refrigerant
If the system cannot be charged with the
specified amount of refrigerant, or can be
charged with a only a small amount at a time
(approximately 150g each time),turn the unit on
in cooling mode; however, one time is not
sufficient, wait approximately 1 minute and then
repeat the procedure.
5).If the electronic scale displays the proper
weight, disconnect the charge hose from the
3-way valve’s service port immediately.
If the system has been charged with liquid
refrigerant while the air conditioner is on, turn
off the air conditioner before disconnecting the
hose.
6). Mount the valve stem caps and the service
port.
Use a torque wrench to tighten the service port
cap to a torque of 18N.m.
Be sure to check for gas leakage.
13.5 Drainage pipe installation
Install the drainage pipe as shown below and
take
measures
against
condensation.
Improperly installation could lead to leakage
and eventually wet furniture and belongings.
13.5.1 Installation principle
Ensure at least 1/100 slope of the drainage
pipe
Adopt suitable pipe diameter
Adopt nearby condensate water discharge
13.5.2 Key points of drainage water pipe
installation
Summary of Contents for HP Series
Page 8: ...5 2 2 Part names of Indoor Outdoor units Cassette Units...
Page 9: ...6...
Page 10: ...7 Ceiling floor Units...
Page 14: ...11 2 3 2 7 Outside Water Pump for Optional When Ceiling Installation...
Page 24: ...21 Ceiling floor Units...
Page 28: ...25 YFKE18BXTMCM RX YFJE18BXTMCM RX YFKE24BXTMCM RX YFJE24BXTMCM RX...
Page 43: ...40 6 2 Outdoor Unit YUKE18BYTMCMO X YUJE18BYTMCMO X YUKE24BYTMCMO X YUJE24BYTMCMO X...
Page 44: ...41 YUKE12BYTMCMO X YUJE12BYTMCMO X...
Page 57: ...54 12 Field Wiring 9K 24K...
Page 104: ...101 P U P V...
Page 105: ...102 P W P N...
Page 108: ...105 High temperature protection of IPM board diagnosis and solution P2...
Page 115: ...112 16 4 16 J4 Malfunction...
Page 119: ...116...