![Xylem WEDECO EFFIZON SMOevo Series Manual Download Page 68](http://html1.mh-extra.com/html/xylem/wedeco-effizon-smoevo-series/wedeco-effizon-smoevo-series_manual_4680067068.webp)
Manual Ozone Generating System SMOevo
Error! Use the Home tab to apply Überschrift 1 to
the text that you want to appear here.
Rev. 1.0
Page 68 of 91
NOTICE!
Hazard due to improper operation!
Risk of damage to the system.
It is absolutely necessary to ensure that neither any liquid nor
humid gas of downstream reactors or ozone introduction
systems is able to flow back into the ozone system. Make
sure that appropriate equipment is available.
Only introduce ozone into the mixing appliance if the
minimum flow quantity of the cooling medium, as described in
the manual, has been reached or exceeded and the ozone
destructor is operational.
7.1.7 Purging the System for Drying Out Purposes
Prior to commissioning the ozone system for the first time, or after carrying out modifications
to the connection lines, ensure that all moisture is removed from the gas lines.
Purge the gas flow circuit until an atmospheric dew point of -70 °C (~3 ppm) at the outlet of
the ozone generator is ensured. Depending on the moisture load, the purging process may
take between 4 and 24 hours.
Only use dry air free of oil and grease, dry nitrogen or
oxygen for the purging process. If purging the ozone system
with oxygen, observe all the regulations concerning the
handling of oxygen.
Refer to section Hazardous Substance Oxygen
Make yourself familiar how to operate the touch panel.
Refer to section Operation
.
After the purging phase is completed, the ozone system can be switched off.
The system is ready for initial start-up.