Original Operating Instructions
BATx0280-ES-1-400-1 (Outdoor)
Commissioning
O_BATx0280-ES-1-400-1_(Outdoor)_V1.3_GB
Page
46
of
69
4.2
Preparing Commissioning
Prerequisite:
•
Conditions for operation must be fulfilled (Section 11.2).
Procedure:
1.
Ensure
that the Enable switch pressed.
2.
Ensure
that the product is de-energized.
3.
Ensure
that all fuses are inserted (Figure 6).
4.
Ensure
that the motor protecting switch (-F31) is in position
I
5.
Ensure
that the sliding switch of the DC circuit breaker (-Q1) is in position
AUTO
.
6.
Ensure
that the AC circuit breaker (-Q2) is in position
OFF
.
7.
Ensure
that all cables and lines are undamaged, connected correctly and in
proper condition.
8.
Connect
the PE conductor (Section 3.5.1.1)
9.
Connect
the supply voltage (Section 3.5.1.4).
10.
Connect
the batteries to the corresponding terminals (Section 3.5.1.3).
11.
Connect
the product to the grid (Section 3.5.1.2).
12.
Ensure
that the screws on all connections and terminals have the correct
torque
.
Summary of Contents for BAT 0280-ES-1-400-1 Series
Page 69: ......