Original Operating Instructions
BATx0280-ES-1-400-1 (Outdoor)
Installation
O_BATx0280-ES-1-400-1_(Outdoor)_V1.3_GB
Page
42
of
69
3.5.2.6 External Current Measurement Device
Required material (not include in scope of delivery):
•
Current measuring device
Procedure:
1.
Locate
the terminal strip (-X3) (Figure 19).
2.
Open
the corresponding cable ducts.
3.
Route
the cable through the cable entry grommet.
4.
Remove
the cable bridges between terminals:
(-X3.1) to (-X3.2)
(-X3.3) to (-X3.4)
(-X3.5) to (-X3.6)
5.
Connect
the measuring devices to the following terminals:
For phase
L1
(-X3.1) to (-X3.2)
For phase
L2
(-X3.3) to (-X3.4)
For phase
L3
(-X3.5) to (-X3.6)
6.
Close
cable duct.
7.
Fix
the cable with a cable clamp.