3.5.1.2 AC Connection
Prerequisites:
•
All grid parameters must be fulfilled (Section 11.2.1).
Figure 12: AC connection
Pos.
Description
1
Cable clamp
2
Cable entry grommet
3
L1 phase connection
4
L2 phase connection
5
L3 phase connection
6
Neutral conductor connection
7
PE conductor connection
8
Protective cover
Procedure:
1.
Observe
the sequence (Figure 12).
2.
Route
the cables through the cable entry grommets.
3.
Connect
the cables for L1, L2, L3 and N to the corresponding terminals (-X14).
4.
Tighten
the screws with a torque of
28 Nm
.
NOTICE: The terminals are suitable for conductor cross-section of maximum 240 mm
2
.
5.
Fix
the cables with cable clamps.