INSTALLATION
6 720 648 726 (2011/07)
19
8
INSTALLATION
This section explains how to install the boiler in a
professional manner.
8.1
INSTALLING THE BOILER
Observe the installation distances of the concentric flue
gas system in the separate flue gas system manual.
B
Before starting installation check that the carrying
capacity of the wall is sufficient for the boiler weight.
B
Remove the packaging and dispose of it in an
environmentally manner.
B
Measure the installation height (
Æ
chapter 7
"Dimensions of boiler", page 17).
B
Mark out both holes using the wall bracket (step 1)
using a spirit level.
B
Drill 2 holes in the wall (step 2).
B
Insert the 2 enclosed plugs in the drilled holes
(step 3).
B
Install the wall bracket, using the 2 enclosed screws
(step 4).
Fig. 8
Installing the wall bracket
B
With two people, lift the boiler by holding it by its
back and by the transport rail at its bottom and install
it on the wall bracket (
Æ
B
Slide the boiler into place (
Æ
fig. 9).
Fig. 9
Sliding the boiler
B
Level the boiler using the set screw and a spirit level
(
Æ
fig. 10).
Fig. 10 Aligning the boiler with the set screw
B
Remove the protective covers from the bottom of the
boiler (
Æ
CAUTION:
Damage to the installation.
B
Do not remove the polystyrene foam
bottom slab, otherwise the connection
injectors might be damaged.
B
Do not lift the boiler by holding it by the
door over the BC10 (
Æ
B
During installation work, cover the boiler
and the flue gas adapter to prevent site
dirt from entering.
6 720 648 726-008.1TD
Some residual water from final testing may
leak away.
6 720 648 726-009.1TD
6 720 648 726-010.1TD