Cable lengths table 

____________________________________________________________________________ 

10 

 

Maintaining the cable functions 

According to valid national regulations.  
 
The cable network for smoke ventilation 

systems („Cable system“) ends at the interface (junction box) for the 

actuator! 
The flexible, heat resistant connection cable of the smoke ventilation system actuator is part of the system 
component ‚electric motor actuation' and does not belong to the electrical installation! 
 

We recommend in all cases to discuss the type of cable routing with the competent fire fighting 
authorities. 

 
 

Cable length table 

 
For determining the maximum permissible cable lengths between the smoke control unit and the actuators, 
taking into account the specified cables cross sections, please refer to the following table: 
 
Maximum motor current:   

4A  

(

Note:

 Be aware of the overall capacity of the smoke control unit!) 

 
Maximum cable length: (always routed from the central smoke control unit to the last junction box) 
Actuating current: Sum of all motor currents per group module 
 

Note:  

Do not use the green/yellow wire! 

 

Per motor supply line, 3 wires are required ( 2 wires current carrying /1 wire for monitoring ) 

 

 

Cross section 

3 wire 

5 wire 

3 wire 

5 wire 

3 wire 

 

1,5 mm² 

1,5 mm² 

2,5 mm² 

2,5 mm² 

4 mm² 

Actuator current  

in Amps 

 

(2 wires in 

parallel) 

 

(2 wires in 

parallel) 

 

84,00 m 

168,00 m 

140,00 m 

280,00 m 

224,00 m 

42,00 m 

84,00 m 

70,00 m 

140,00 m 

112,00 m 

28,00 m 

56,00 m 

46,67 m 

93,33 m 

74,67 m 

21,00 m 

42,00 m 

35,00 m 

70,00 m 

56,00 m 

(The information is valid for ambient temperatures of 25°C) 
 

Formula for the calculation of the maximum cable length 

Permissible max. voltage drop in the line UL :   2 Volt 
 
 
max. cable length = permissible voltage drop(

UL

) x conductivity of copper(

56

) x cable cross section(

A

 

 

   

max. actuator current total (

I

) in amps 

x 2

 

 
Permissible cable length for the break glass unit supply cable when using......4x2x0.8mm:     

up to 200m

 

 
The motor connection cable length to the junction box (or control module) must not exceed 

10 m

 

Summary of Contents for WSC 304 6102

Page 1: ...able of contents Safety information Operating elements and fuse review Technical data Installation Cable lengths table Cable plan Standard wiring diagram Various wiring diagrams Commissioning Maintena...

Page 2: ...e insulation of the power supply cable in place up to the mains terminal Manufacturer s declaration The central control system is exclusively designed for the automatic closing of smoke extraction sys...

Page 3: ...Operating elements and fuse review ____________________________________________________________________________ 3...

Page 4: ...moke control unit the red LED in the break glass unit and the red LED at the tripped automatic detector extinguish Resetting a trip caused by high temperature The smoke extraction system can be closed...

Page 5: ...rated in the button Ventilation closed The actuators close after pressing the CLOSED button Display The ventilation open LED in the ventilation button has extinguished only with LED integrated in the...

Page 6: ...at there is no fault An alarm signal has first priority SW 1 2 ON Forwarding the alarm signal WSA 301 After 3 min it will stop SW 1 2 OFF Forwarding the alarm signal WSA 301 as long as the alarm is tr...

Page 7: ...terminal for 2 wire BUS cable for the feedback of malfunctions in cascaded control units to the break glass unit connected to the master smoke control unit Alarm message 1 x change over contact max l...

Page 8: ...y every 2 min Review of fuses Mains 630mA slow blow Motor 4 A slow blow Battery 630mA medium slow blow Type of connection to external Mains screw terminal plug screw terminals 0 5 2 5qmm Cable monitor...

Page 9: ...control and remove the housing top section door from the housing bottom section Fasten the housing bottom section in the wall cut out cut out dimension 335 x 350 x 95 and refit the housing top sectio...

Page 10: ...imum cable length always routed from the central smoke control unit to the last junction box Actuating current Sum of all motor currents per group module Note Do not use the green yellow wire Per moto...

Page 11: ...Cable plan ____________________________________________________________________________ 11...

Page 12: ..._____________________________________________________ 12 WLA 330 WLA331 WSA 300 WSC 304 6102 WSK 320 WSK 330 First or secundary Break glass unit If only one break glass unit usa a main break glass uni...

Page 13: ...Various wiring diagrams ____________________________________________________________________________ 13...

Page 14: ...from one face of the supplied foam rubber Glue each foam rubber to the bottom side of the accumulators Connect the accumulators to the black accumulator bridge according to the wiring diagram then co...

Page 15: ...b The green mains and operating LED s are OFF the yellow accumulator Led is flashing control unit in the accumulator mode The malfunction message at the break glass unit is ON c The ventilation butto...

Page 16: ...and clamping screws for firm seating Carry out a test run of the entire system see chapters Start up and Test Run Only have defective units repaired in our factory Only install original spare parts C...

Reviews: