Installation
IMPORTANT: Before beginning the installation it is important to have an understanding of the
layout plan. Review all drawings and follow the layout plan drawing as configured.
IMPORTANT: These procedures are not rated for environments that require seismic installation.
For seismic procedures, see 270A672.
Floor Frame and Door Frame Assembly
This procedure is described for a 36" (914 mm) or 48" (1219 mm) door.
For 90" (2286 mm) Double Doors, see the instructions in 270A837.
1. Locate the floor frame sides, connect brackets and the four corner sections.
2. With the padded side towards the ground,
lay all of the pieces out according to
the layout plan to create the outline
of the room, leaving an opening for
the door.
NOTE:
A corner section must be placed in
each corner regardless of the door
position and size.
If the optional Inset Floor is being installed, follow the procedure
in 271A210 before proceeding.
The SoundLok door frame is shipped fully assembled in a
wooden crate.
3. Remove the screws holding the side and top panels of
the door crate.
4. Lift the door frame assembly from the crate and transport
it to the final set-up location.
Top
Panel
Side
Panel
The door frame assembly is
heavy. More than one person
must lift the assembly from
the crate and set into place.
!
CAUTION
Do not slide the door
assembly gaskets on any
surface.
!
CAUTION
Door
Crate
Door
Frame
Assembly
36" (914 mm)
Door
45" (1143 mm)
Opening
48" (1219 mm) Door
60" (1524 mm)
Opening
Double
Door
90" (2286 mm)
Opening
Floor
Frame Side
Corner
Section
Connect
Bracket