Commissioning protocol IP 60
Granudos 45/100-S5
Z:\org-wdt\02 Qualitätsmanagement\ISO 9001\MS - Originale - Formuale, Prüfbericht etc\WDT Inbetriebnahmeprotokoll IP\WDT IP 60 GR 45-100-S5 EN FO 00.doc
Page
1
of
2
This protocol has to be completed by the commissioning technician! All warranty claims expire when no completed
and signed commissioning protocol is available!
Object:
Date: __.__.____
City, Street, Street number:
Device type:
Year of construction:
Serial no.:
Activity
Completed Comment
1
Dissolving system (consider 6 seconds switching delay!)
1.1
Install the roller carriers of the hose pumps, see operating
instructions, section 5.2.1
1.2
Connect the dosing canister and attach the chlorine barrel
1.3
Bleed the operating water pump
1.4
Adjust the water flow in the dissolving system
1.5
Check the pressure switch (41) Ball valve intake closed, device
stopped, fault display
1.6
Adjust the pressure switch (41)
1.7
Check flow switch: Outlet ball valve closed, dosing stopped, fault
indication
1.8
Set the water level in the rinsing tray
1.9
Check level switch: Switching body high - dosing stopped, fault
indication
1.10
Check the level switch: Switching body low - device stopped, fault
indication
1.11
Check the floater valve function - flow reacts gently
2
Chlorine dosing technology
2.1
Heating function: Dosing pipe warm?
2.2
"Empty-switch" function: Drum turning - fault indication
2.3
Dosing motor function: Chlorine starting test program
2.4
Check the tensioning straps and safety belt
2.5
Introduction to drum changing, see operating instructions, section
5.2.3
3
pH-reducer dosing system
3.1
Check the empty switch: Pull the suction lance out of the canister -
see display
3.2
Check the dosing pump: Test program
4
Control - after opening the controller
4.1
All connectors firmly latched
5
Buffer tank (option)
5.1
Check function of the control and alarm switches in the tank:
Indication on the display
5.2
Check prevention of the on site dosing pump reflux
5.3
Check the reflux prevention in filling system
6
Other
6.1
Clean the GRANUDOS system
6.2
Discuss the operating instructions and hand them over
Continue to page 2