4211-1661 01/28/2022
APPENDIX: SYSTEM INSTALLATION
APPENDIX: SYSTEM INSTALLATION
page 6
SECTION 6: OPERATIONAL TEST
After controls and slave generators are connected
After connecting the control, temperature sensor and secondary steamer(s) to the Primary generator:
1. Assure power and water are on.
2. Press the control’s ON/OFF switch. A light vibration should be felt in the control and the control’s display should light-up.
(see control instructions included with control kit)
3. Allow 10 minutes for the steam to start.
The time to see steam start will vary depending on each generator’s power rating
.
4. Once the steam starts, press the ON/OFF switch. The steam should stop; there shouldn’t be any water flow.
5. Press the ON/OFF switch.
6. Within one minute the units should again produce steam. The generators should call for water once every two minutes or more depending
on their power rating. It’s normal for the flow of steam out the steam head to slow for up to 10 seconds each time a unit calls for water.
7. The units will shut down automatically in 60 minutes (or the time set using an interior or exterior control). When the time runs out the steam
will stop and there should not be any water flow.
THE SYSTEM IS NOW READY FOR OPERATION.
60m/24HR
NORM/EXT
°F/°C
4.
SET OPTION JUMPERS
Set jumpers in the Primary steamer as instructed in the single steamer instructions.
Secondary steamers should have their jumpers placed on only one pin (
see diagram at right
).
4.
CONNECT CONTROLS
Connect controls only to the Primary steamer. Refer to the individual steamer instructions for requirements.
SECTION 5: WIRING INSTRUCTION (continued)