INSTALLATION of the SOLAR PANEL and RAIN SENSOR  

The  solar  panel  must  be  mounted  with  airspace 
underneath for cooling and performance efficiency; as 
well as maintain the product life span.  

1. Lay the solar panel face down on a flat surface. 

Take care not to scratch the solar panel. 

2. Insert two stainless steel nuts into the channel of 

the  perimeter  frame;  one  each  on  the  two  short 
sides. 

3. Use  two  stainless  steel  bolts  to  attach  the  two 

bracket  tabs  to  the  frame  with  the  two  nuts 
inserted into the channel. Do not fully tighten at 
this time. 

4. Use the remaining stainless steel bolts and nuts to 

attach the mounting bracket to the solar panel. 

5. Install  the  solar  panel  and  bracket  on  to  the 

exterior  of  the  building  near  the  operator 
installation location. 

6. Tilt  and  rotate  the  solar  panel  to  maximize  the 

solar  panels  exposure  to  the  Sun.  Alignment 
towards  the  southern  sky  is  recommended  for 
most  locations  in  North  America  for  best 
exposure to mid-day sun. 

7. Tighten all the fasteners to secure the solar panel 

orientation. 

8. Route  and  waterproof  the  pigtail  wiring  to  the 

interior of the building where the operator is to be 
installed. 

9. Install the rain sensor and bracket on the exterior 

as level as possible near the operator. 

10. Route  and  waterproof  the  wiring  to  the  interior 

where the operator will be installed. 

It  is  highly  recommended  to  only  use  the  wiring 
provided for the solar panel and rain sensor. 

 

 

Installation and User Manual 

5

Revision 8.12.2015

INSTALLATION of the SOLAR PANEL and RAIN SENSOR  

The  solar  panel  must  be  mounted  with  airspace 
underneath for cooling and performance efficiency; as 
well as maintain the product life span.  

1. Lay the solar panel face down on a flat surface. 

Take care not to scratch the solar panel. 

2. Insert two stainless steel nuts into the channel of 

the  perimeter  frame;  one  each  on  the  two  short 
sides. 

3. Use  two  stainless  steel  bolts  to  attach  the  two 

bracket  tabs  to  the  frame  with  the  two  nuts 
inserted into the channel. Do not fully tighten at 
this time. 

4. Use the remaining stainless steel bolts and nuts to 

attach the mounting bracket to the solar panel. 

5. Install  the  solar  panel  and  bracket  on  to  the 

exterior  of  the  building  near  the  operator 
installation location. 

6. Tilt  and  rotate  the  solar  panel  to  maximize  the 

solar  panels  exposure  to  the  Sun.  Alignment 
towards  the  southern  sky  is  recommended  for 
most  locations  in  North  America  for  best 
exposure to mid-day sun. 

7. Tighten all the fasteners to secure the solar panel 

orientation. 

8. Route  and  waterproof  the  pigtail  wiring  to  the 

interior of the building where the operator is to be 
installed. 

9. Install the rain sensor and bracket on the exterior 

as level as possible near the operator. 

10. Route  and  waterproof  the  wiring  to  the  interior 

where the operator will be installed. 

It  is  highly  recommended  to  only  use  the  wiring 
provided for the solar panel and rain sensor. 

1.  Review  the  separate  instructions  for  motor 

operation  and  open  the  skylight  fully  with  the 
remote control.

2.  Connect the solar panel to the wire on the exterior 

of the skylight at the low side. The connector can 
only  go  together  one  way  and  will  ‘click’  when 
locked together.

3.  Locate  the  solar  panel  on  the  skylight  frame  as 

shown below, centered side to side. Install the 
panel with the screws supplied.

4.  Close the skylight to complete the installation.

NOTE: The skylight needs to be installed on the roof before attaching the solar panel.

Summary of Contents for Solar Smart GSVMS

Page 1: ...ANUAL 800 388 0293 Fax 207 216 4562 csm wascoproducts com www wascoskylights com Eastern Facility 85 Spencer Drive Unit A Wells ME 04090 Western Facility 6645 Echo Avenue Reno NV 89506 with Rain Senso...

Page 2: ...hment link on chain is fastened to the sash by a release pin 7 AC trickle charger included 8 Adaptable to awning and hopper windows and skylights Remote Highlights 1 Large and readable display with bi...

Page 3: ...d bracket g bracket ket tabs UIRED ing the operator ing the chain clip ing the solar panel and bracket DO NOT INSTALL THE BATTERIES UNTIL DIRECTED TO DO SO Chain Clip Battery Cover Operator Battery AC...

Page 4: ...up the remote if the LCD display has powered off 2 Press ZONE to choose a single zone 1 thru 9 of operators or ALL to operate all operators in all zones 3 Press OPEN or CLOSE to open or close the win...

Page 5: ...Manual sion 8 12 2015 ON of the SOLAR PANEL and RAIN SENSOR panel must be mounted with airspace for cooling and performance efficiency as intain the product life span e solar panel face down on a fla...

Page 6: ...ion 7 ZONE ALL and the temperature should now be displayed Installation and User Manual 7 Revision 8 12 2015 INITIAL REMOTE SETUP and CONFIGURATION The following are applicable for configuring the mai...

Page 7: ...The remote will need to be paired within 2 minutes or the operator will default back to the previous settings 1 Remove the battery cover from the operator If connected disconnect the battery connecto...

Page 8: ...operator zones ID numbers and or adding additional operators can only be performed using the main remote The changed settings would then need to be re sent from the main to the secondary remote s Ens...

Page 9: ...from the main remote It will wait for 30 seconds 2 MAIN REMOTE STEPS a Press and hold MODE release when PAIR SET is displayed b Press MODE twice to move past RE ZONE to display M in the upper right c...

Page 10: ...ON or OFF for one second then SUCC for 2 seconds indicating success Press MODE a few times to return to the home screen a If setting not successful LCD displays FAIL for 1 second then returns to the...

Page 11: ...unction off 9 Press ENTER 10 ST is now displayed and flashing Press MODE to return to the home screen OR press to scroll and set other features 11 The Time To Close selection will be retained in memor...

Page 12: ...e operator s is open The factory setting MAX OPEN limit is set to open up to 80 of full open position 1 Press any key to wake up the remote if the LCD display has powered off 2 Press MODE 3 Press ZONE...

Page 13: ...Press ENTER 8 Press to set the desired temperature or NULL to turn function off for this zone 9 Press ENTER to save your selection The temperature in which the operator will run has now been set Next...

Page 14: ...lar moment in time This measurement is highly variable and depends directly upon the level of sunlight on the solar panel Be aware of external influences which affect the light level these are directi...

Page 15: ...hen PAIR SET is displayed 3 Press MODE again to display RE ZONE 4 Press ZONE as necessary to choose the appropriate zone 1 thru 9 of the operator to be moved to another zone 5 Press ENTER to save your...

Page 16: ...se set MAX OPEN 4 Temperature change must be maintained for 10 minutes before the temperature control TC function will operate For more Trouble Shooting Tips please visit www SolarSmartOpener com ADVA...

Page 17: ...se record your Remote settings for ease of reference as well as assist in troubleshooting ZONE ID Location 1 1 2 3 4 5 6 7 8 9 2 1 2 3 4 5 6 7 8 9 3 1 2 3 4 5 6 7 8 9 4 1 2 3 4 5 6 7 8 9 5 1 2 3 4 5 6...