43
1.
Insert new gaskets in all gas fittings
that have been opened and then
tighten those fittings.
2.
Open the gas shut-off valve.
3.
Check the inlet joints of the gas train
for tightness.
4.
Start the burner (see page 18).
5.
Check the outlet joints of the gas train
and fittings between the fan and the
boiler door and between the fan and
the Venturi pipe for tightness.
Implementing final checks
1.
Carry out final checks in accordance
with the points on pages 27 to 29.
2.
Record the actual values in the report
(on page 86).
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5794 780 GB