ALT-8000 Getting Started Manual
26
STEP
PROCEDURE
12. Select
Save & Return
to store value and return to the
Info Screen window. Select the Done key to return to
Test Setup (General Tab). The test set is now ready to
perform the Linear Altitude Ramp Test.
9
LINEAR ALTITUDE RAMP TEST
The Linear Altitude Ramp Test performs a linear up and
down altitude ramp, verifying adequate UUT loop gain. This
is the lowest level of flight-line testing recommended to
confirm reported problems, or to verify system operation
after LRU replacement.
Perform the following steps to complete the Linear Altitude
Ramp Test:
STEP
PROCEDURE
1. Confirm the following settings and change as necessary.
Control
Start Altitude = 0 ft (50 to 75 ft for pulse type)
Stop Altitude = 2,500 ft (or maximum for system
under test)
Altitude Rate = 1,000 ft/min (2.5 mins duration)
NOTE:
Altitude Rate is selected 1 to 120,000 ft/min. If trip
operation is to be verified, a recommended rate of
<1000 ft/min should be entered.
All manuals and user guides at all-guides.com
Summary of Contents for ALT-8000
Page 1: ...ALT 8000 Radio Altimeter Getting Started Manual All manuals and user guides at all guides com ...
Page 2: ...all guides com ...
Page 8: ...all guides com ...
Page 14: ...all guides com ...
Page 20: ...all guides com ...
Page 26: ...all guides com ...
Page 32: ...all guides com ...
Page 38: ...all guides com ...