20
9.2
Assembly procedure
1. Put the boiler on the required standpoint (it is necessary to respect the demands on boiler positioning
stated in chap. 8) according to the project documentation. We recommend to transport the boiler to
the determined standpoint while on a pallet, possibly still wrapped in protective packing. If this isn’t
possible due to the space restrictions the boiler is transported without the packing by transferring it by
using the boiler base plate in which there are on the left and right hand side prepared two circular
openings determined for putting on the “ removal hooks”. By means of hooks the boiler can be lifted and
transported to the required standpoint. It is forbidden to use the gas and heating water pipes for
lifting the boiler. The boiler must stand fast on the incombustible pad in its vertical position and well–
balanced.
2. Mount the TE-joint at the heating water outlet from boiler, the discharge valve at the heating water inlet
and automatic bleeder valve (Fig.no.12) at the heating water outlet. The parts are delivered together with
the boiler.
3. Connect to the heating system according to project documentation.
ídržný plech pro
tného toku spalin
ovací ventil
nástavec
horizontálního
p
ř
erušova
č
e tahu
(jen pro 7
č
l.velikost
horizontální
p
ř
erušova
č
tahu
odbo
č
ka TE
redukovaná 90
vypoušt
ě
cí ventil
Fig. no. 12
Connection to the heating system and the draught diverter assembly
Number of sections
3
4
5
6
7
natural gas– output in kW
12-17
18-26
27-34
35-41
42-49
D
110
130
160
170
180
T
340
420
500
580
660
T1
165
205
245
285
325
B
485
485
570
740
740
L
733
733
733
773
773
Fig. no. 13
Dimensions for connection
T - kus
retaining plate for
combustion products
return flow fuse
automatic
bleeder valve
T-piece
horizontal draught diverter
extension
(only for 7 sectional size)
horizontal draught diverter
TE extension reduced 90
discharge valve
Summary of Contents for GRAND G 36
Page 1: ...Hercules U26 N vod k obsluze VIADRUS GRAND G 36 MANUAL FOR BOILER OPERATION AND INSTALATION...
Page 34: ...34...
Page 36: ...36 Date of revision 16 2013 GB...
Page 37: ...Hercules U26 N vod k obsluze VIADRUS GRAND G 36 MANUAL FOR BOILER OPERATION AND INSTALATION...
Page 54: ...18...
Page 58: ...22...
Page 60: ...24 Date of revision 32 2013 GB...