Figure 2-9 Installing the guide rail
1. The guide rail holder must be close to the front of the rack.
2. Any end of one guide rail has four installation holes (see Figure 2-8), do not use
the two installation holes in the middle when fixing the guide rail. It is recommended
to use the top and bottom installation hole (from top to bottom, installation hole 1
and installation hole 4).
The guide rail installation is finished, as shown in Figure 2-1
0
.
Figure 2-10 Guide rail installation completed
3. Place the UPS on the guide rails in the rack, and push it completely into the rack. Use four
M6 × 16 screws to fix the UPS in the rack through the brackets, as shown in Figure 2-1
1
.
Ve
rtiv
UPS
Rack
Bracket
Screw (4pcs)
Guide rail
Figure 2-11 Installing the UPS
Guide railscrew (4pcs)
Guide rail
Guide rail holder
Square hole