Single UPS Installation And Commissioning
This chapter introduces the installation, cable connection and commissioning of the single
UPS.
Each site has its own peculiarity, so this chapter provides general installation procedures and
methods for the installation engineer who should conduct the installation according to the
actual conditions.
Professional installation
1. The UPS should be installed by a qualified engineer in accordance with the
information provided in this section. In the event of any problems, contact your
local Vertiv service center immediately.
2. The UPS must NOT be switched ON without the approval of the commissioning
engineer.
3. For other equipment which is not introduced in this manual, the detailed
information about mechanical installation and electrical installation are delivered
with the equipment.
3-phase 5-line for power input
The UPS can be connected to 3-phase 5-line (A, B, C, N, PE) TN, TT and IT AC
power distribution system (IEC60364-3).
2.1
Unpacking Inspection
The UPS adopts the wooden box. Unpacking steps are as follows:
1. Remove the side panels and top cover.
Use a hammer or straight screwdriver to straighten the connection hook that connects the
side panels to the top cover, as shown in Figure 2-1.
Figure 2-1 Straightening the hook