Vertiv™ NetSure™ IPE Series -48 VDC Outdoor Rectifier Installation and User Manual
Proprietary and Confidential © 2022 Vertiv Group Corp.
33
2.5.3
Wall Mounted Procedure
NOTE!
Torque all hardware to the values shown in the illustrations.
1.
Unpack the rectifier, Li-ion battery and mounting accessories.
2.
Drill appropriately sized holes for the customer provided M10 wall anchors being used into the wall as shown in Figure
2.22. Install the M10 wall anchors into the holes (Figure 2.23).
3.
Install mounting bracket to wall. Refer to Figure 2.24.
4.
Install mounting bracket to Li-ion battery. Refer to Figure 2.25.
5.
Install mounting bracket to rectifier. Refer to Figure 2.26.
6.
Install Li-ion battery to wall. Refer to Figure 2.27.
7.
Install rectifier to wall. Refer to Figure 2.28.
Figure 2.22 Wall Hole Distance (Unit: mm)
Figure 2.23 Expansion Bolt Installation
M10*80mm
P/N:26020787(4x)
Dia: D12mm