2. Pre-Installation Requirement
8 Green X / X18 (Model: PHT-75CHS) Installation Manual
2. Pre-Installation Requirement
2.1
Room Requirements
The location of this equipment must allow for the high
visibility of the patient by the operator, and the operator
should be as about the patient as possible.
This equipment must not be installed on thick carpets
for stability reasons.
Anti-static floor materials must be used around the
equipment.
The PC monitor, emergency stop switch, and X-ray
exposure switch must be installed near the operator to
manage them simultaneously in an emergency.
<Without CEPH Unit (optional): 2,500 mm (L) x 1,700 mm (W) or wider >