Installation
90
10.9.3.
Battery module registration
In the
second
step, the serial number of
the battery module must be entered. It can
be found on the ID label of battery
module.
Afterwards, select
"Continue".
10.9.4.
Grid parameter configuration
For configuration of grid parameters,
select the respective standard in the
"Country code"
drop-down menu.
Check the values and adjust them as
necessary to the requirements of the local
grid operator.
Afterwards, select
"Continue".
10.9.5.
Function test
To start the automatic status check, select
"Start".
Please note:
This may take a few
minutes.
If everything is in order, a green
checkmark is displayed.
Failed tests are indicated by a red cross.
Please restart the function test.
If the test fails again:
Make sure that the cabling is correct.
Switch off the energy storage system.
The entered data is saved.
Summary of Contents for Pulse neo Series
Page 1: ...VARTA STORAGE GMBH OPERATING MANUAL VARTA pulse neo...
Page 2: ...Leerseite Pagina vuota Page blanche Blank page...
Page 4: ...Leerseite Pagina vuota Page blanche Blank page...
Page 32: ...General information 32 2 4 2 ID label of battery module 2 4 3 Unlock code label...
Page 64: ...Installation 64 Three Phase Single Phase Not permitted...
Page 67: ...Installation 67 All Dimensions in mm Fig 2 Dimensions at the mounting plate...
Page 145: ...Subject to modification Appendix Appendix 1 Connection diagram of TT system...
Page 146: ...Subject to modification Appendix 2 Connection diagram of TT system with data logger...
Page 147: ...Subject to modification Appendix 3 Connection diagram of TN C system...
Page 148: ...Subject to modification Appendix 4 Connection diagram of TN C system with data logger...