0020193968_05 ecoTEC exclusive Installation and maintenance instructions
19
2.
Connect the product to the gas line in accordance with
the recognised rules of technology.
3.
Remove the residues from the gas line by blowing
through the gas line beforehand.
4.
Purge the gas line before start-up.
7.4
Checking the gas line for leak-tightness
▶
Check the entire gas line properly for leak-tightness.
7.5
Installing the hot and cold water connection
1
1.
Make the water connections
(1)
in accordance with the
relevant standards.
2.
Ensure correct water pressure and flow requirements
and that any expansion can be accommodated with the
cold supply pipe work.
7.6
Connecting the heating flow and heating
return
1
▶
Establish the heating connections
(1)
in accordance with
the relevant standards.
7.7
Installing the discharge pipe on the
expansion relief valve
1.
Install the discharge pipe for the expansion relief valve
so that it does not interfere with the removal and fitting
of the lower section of the condensate trap.
1
2.
Install the discharge pipe as shown (do not shorten).
3.
Make sure that the end of the pipe is visible.
4.
Ensure that discharged water or steam cannot cause
injury to persons or damage to electronic components.
5.
Ensure the discharge pipe work is installed, routed and
terminated correctly to minimise the risk of freezing up.
7.8
Connecting the condensate discharge pipe
Danger!
Risk of death from escaping flue gases!
The condensate siphon's condensate dis-
charge pipe must not be connected to waste-
water pipework because, otherwise, the in-
ternal condensate siphon may be drained
fully and flue gas may escape.
▶
Do not connect the condensate discharge
pipe tightly to the waste-water pipework.
A
3
2
1
The product is equipped with a condensate siphon
(1)
. (The
filling height is 145 mm). The condensate siphon collects the
condensate that has formed in a vessel with a volumetric ca-
pacity of approx. 200 ml and allows the contents to intermit-
tently drain into the drain pipe. This minimises the risk of the