7
The boilers (with the exception of the 90-75 LP product)
are factory equipped for operation at altitudes ranging from
0-10,000 feet above sea level. No changes to the factory settings
are required for installations from 0-5,000 feet above sea level.
For altitudes from 5,000-10,000 feet above sea level the gas
manifold pressure will need to be adjusted based upon calorific
(Btu) value of supply gas (contact local gas utility or distributor
for this value). For specific settings refer to Table #1 for natural
gas applications and Table #2 for LP gas applications. Instruc-
tions on how to adjust the gas manifold pressure settings are
shown in
Figures #17 & #18
.
Note that 90-75 LP applications for 5,000 - 10,000 feet above
sea level will require an orifice change as well as a gas manifold
pressure adjustment based upon calorific (Btu) value of supply
gas. Refer to Table #2 for altitude orifice kit part number. For
replacing the orifice refer to specific instructions included with
the kit.
TABLE #1: SERIES 90 NATURAL GAS
series 90-50
stock Factory
Btu Value of Natural Gas++
settings
750
850
950
1000
1050
Altitude in Ft.
0-5,000
5,000-10,000
Normal Input (MBH)
50
–
–
–
–
–
Manifold Pressure In W.C.
2.5
4
4
3.5
2.5
2.5
Orifice
43331094
43331094
series 90-75
stock Factory
Btu Value of Natural Gas++
settings
750
850
950
1000
1050
Altitude in Ft.
0-5,000
5,000-10,000
Normal Input (MBH)
75
–
–
–
–
–
Manifold Pressure In W.C.
2.5
3.5
3.5
2.5
2.5
2.5
Orifice
43331092
43331092
series 90-100
stock Factory
Btu Value of Natural Gas++
settings
750
850
950
1000
1050
Altitude in Ft.
0-5,000
5,000-10,000
Normal Input (MBH)
100
–
–
–
–
–
Manifold Pressure In W.C.
2.5
3.5
3.5
2.5
2.5
2.5
Orifice
43331090
43331090
++Contact local gas utility or distributor for Btu value of gas.
BOILERS FOR USE AT HIGH ALTITUDE
Summary of Contents for UB100
Page 15: ...15 Near Boiler Piping Figure 2 Single Zone Boiler Piping ...
Page 16: ...16 Figure 3 Multi zone Boiler Piping With Zone Valves Near Boiler Piping ...
Page 19: ...19 Figure 6 Diaphragm Type Expansion Tank Piping Near Boiler Piping ...
Page 20: ...20 Figure 7 Conventional closed type Expansion Tank Piping Near Boiler Piping ...
Page 27: ...27 Combustion Air and Vent Pipe Figure 11 Combustion Air and Vent Piping ...
Page 32: ...32 Electrical Wiring Figure 13 Field Wiring Connections ...
Page 53: ...53 DETAILED SEQUENCE OF OPERATION ...
Page 57: ...57 TROUBLESHOOTING CHART 2 TROUBLESHOOTING ...
Page 58: ...58 TROUBLESHOOTING CHART 3 TROUBLESHOOTING ...