7.
Push the plate heat exchanger (2) in and to the
back of the casing unit (3). Fit the two
brackets (1).
8.
Install the frame sections.
9.
Install panel and doors.
Installing the upper AHU casing unit
Put the upper casing unit from above onto
the lower casing unit
If there is enough space above the AHU, the entire
casing unit can be put from above, e.g. with a crane,
onto the lower casing unit that contains the heat
exchanger. In this case you may continue with
step 13.
10.
Remove the back panel (1) and the frame sec-
tion (3) from the upper AHU casing unit. If neces-
sary, remove the sealing sheet (2).
Setup and assembly
Setting up and assembling the air handling unit > Installing the plate heat exchanger
Air handling unit X-CUBE
30