Post Placement 

The MATT™ posts are inserted into the soil using an auger or post pounding equipment for placement. 
If an auger is used, ensure diameter is large enough to allow for proper compaction of state/specifying 
agency  approved  fill  material.    All  MATT™  posts  must  be  assembled  within  established  standard 
construction  tolerances,  including  being  plumb.  Compaction  for  all  posts  must  be  within  the 
state/specifying agency guidelines. 

 

Danger: 

It is the responsibility of the installer to ensure all above & below ground utilities 

as well as drainage structures are located, marked, and identified prior to using an auger 
or post pounding tool in accordance with state/ specifying agency

 

guidelines. Failure to 

follow this warning could result in serious injury or death.

 

 

Rigid Pavement and Rock 

If rigid pavement (e.g. concrete or asphalt) of any thickness is encountered within the system, ensure a 
proper “leave-out” area (the specified size of open space as defined in the AASHTO Roadside Design 
Guide)  and/or  per  the  state/specifying  agency  is  provided  around  the  posts  and  filled  with  the  state/ 
specifying agency approved backfill material.   

If solid rock is encountered at post locations 3-6, refer to the state/specifying agency guidelines and/or 
the AASHTO Roadside Design Guide for requirements for embedment depth into the rock and size of 
the hole.  If solid rock is encountered at post locations 1-2, auger a hole in the rock large enough for full 
post embedment and proper compaction of approved fill material. 

 

 

Drilling Holes into rock 

Caution:    It  is  the  responsibility  of  the  installer  to  consult  Occupational  Safety  &  Health 
Administration  (“OSHA”)  silica  respiratory  standard  29  Code  of  Federal  Regulation  (“CFR”) 
1910.134 for debris removal and ensure compliance. 

 

 

Inspect Shipment 

Carefully unpack and inspect all components for damage. Check the received parts against the packing 
list supplied with the system. If any parts are damaged, missing, or unspecified; do not attempt to assemble 
the system and contact Trinity Highway immediately (p. 4). 

 

Warning:  Use only Trinity Highway parts that are specified by Trinity Highway for 
use with the 

MATT™

 for assembling, maintaining, or repairing the 

MATT™.  

Do not 

utilize or otherwise commingle parts from other systems even if those systems 
are other Trinity Highway Products or Systems. 
 
 
 
 
 
 

 

 

Summary of Contents for MATT

Page 1: ...PN 628155 Created February 2022 MATT Median Attenuating TREND Terminal Assembly Manual TRINITY HIGHWAY Ahead of the Curve...

Page 2: ...These instructions are for standard assembly specified by the appropriate highway agency In the event the specified system assembly maintenance or repair would require a deviation from standard assemb...

Page 3: ...gent double sided re directive gating and energy absorbing attenuator end terminal for use with various longitudinal highway barriers in either unidirectional or bidirectional traffic applications to...

Page 4: ...sembly Posts 3 to 5 24 STEP 6 MATT 12 Gauge Transition Guardrail With Fin 4 9 4 1 2 2 858 m 25 STEP 7 MATT 12 Gauge Slotted Intermediate Guardrail With Fin 3 6 3 1 905 m Posts 4 5 26 STEP 8 MATT 12 Ga...

Page 5: ...onal Highway System OSHA Occupational Safety Health Administration PPE Personal Protective Equipment SYTP Steel Yielding Terminal Post TL 3 Test Level 3 Trinity Highway Trinity Highway Products LLC Cu...

Page 6: ...oval proper installation and maintenance of any highway product is the sole responsibility of the state specifying agency WARNING Under NO circumstances shall the rail within the MATT be curved radius...

Page 7: ...ead MATT CR top and bottom posts MATT SYTP with soil plate MATT system line post with soil plate MATT angle strut MATT cable assembly MATT spacers composite offset blocks and various other required ha...

Page 8: ...aint and Pen Straight Edge Level Plumb Line Post Pounder commonly used for driving posts Auger Soil Tamper 5 8 Alignment Tool Drift Pin used to help align panels Locking Pliers and or Pipe Wrench Cali...

Page 9: ...ircumstances shall the rail within the MATT be curved between Post 1 and Post 6 Ensure all MATT post spacings are 6 3 1 905 m on center IMPORTANT When used with rigid barriers i e concrete barrier wal...

Page 10: ...ided around the posts and filled with the state specifying agency approved backfill material If solid rock is encountered at post locations 3 6 refer to the state specifying agency guidelines and or t...

Page 11: ...0G 16 V 5 8 x 2 Hex Bolt A307 16 mm x 51 mm 3403G 6 W 5 8 x 2 GR Bolt Grade 5 A325 16 mm x 51 mm 118614G 62 Y 5 16 Hex Nut 8 mm 3245G 2 Z 5 8 Heavy Hex Nut A563 16 mm 3361G 66 AA 5 8 Round Washer 16 m...

Page 12: ...lowing components hardware are not shown to scale ID A PN 628342B ID B PN 628289A ID C PN 628337A MATT Impact Head MATT 12 Gauge Transition Guardrail With Fin 4 9 4 1 2 MATT 12 Gauge Slotted Intermedi...

Page 13: ...king Plate MATT CR Post 1 Top MATT CR Post 1 Bottom ID M PN 628271G ID N PN 628270G ID O PN 628279G MATT SYTP 6 0 MATT Line Post 6 0 MATT Angle Strut ID P PN 119506G ID Q PN 33909G ID R PN 628348G MAT...

Page 14: ...ID V PN 3403G ID W PN 118614G ID Y PN 3245G 5 8 x 2 Hex Bolt A307 16 mm x 51 mm 5 8 x 2 GR Bolt Grade 5 16 mm x 51 mm 5 16 Hex Nut 8 mm ID Z PN 3361G ID AA PN 4372G ID BB PN 3340G 5 8 Heavy Hex Nut A5...

Page 15: ...8273G 5 16 Flat Washer 8 mm 8 200 mm Composite Offset Block MATT Soil Plate Posts 1 2 ID NN PN 628269G ID OO PN 113660G ID TT PN 3500G MATT Soil Plate W Shaped Posts 3 6 5 8 x 3 50 Hex Bolt Grade 5 A3...

Page 16: ...is fully assembled for Steps 5A and 5B tighten the double single spacers to a snug position with a minimum of two 2 bolt threads protruding beyond the nut for all hardware that was assembled loosely...

Page 17: ...ht of the MATT CR Post 1 Bottom is 4 100 mm 1 0 25mm 0 mm above finished grade Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do...

Page 18: ...MATT CR Post 1 Bottom With Soil Plate is 4 100 mm 1 0 25 mm 0 mm above finished grade T 3391G 2 EA BB 3340G 2 EA MM 628273G 1 EA Use only Trinity Highway parts that are specified herein for the MATT...

Page 19: ...e approximately at finished grade 1 0 25 mm 0 mm BB 3340G 2 EA MM 628273G 1 EA OO 113660G 2 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repai...

Page 20: ...he SYTP Holes are approximately at finished grade 1 0 25 mm 0 mm BB 3340G 6 EA NN 628269G 3 EA OO 113660G 6 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling main...

Page 21: ...Post 6 at location established in Step 1 BB 3340G 2 EA NN 628269G 1 EA OO 113660G 2 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the...

Page 22: ...g maintaining or repairing the MATT Do not utilize or otherwise commingle parts from other systems even if those systems are Trinity Highway systems WARNINGS Ensure the flat washer is between the bolt...

Page 23: ...rinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise commingle parts from other systems even if those systems are Tr...

Page 24: ...only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise commingle parts from other systems even if those systems...

Page 25: ...A AA 4372G 6 EA BB 3340G 6 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise commingle parts from ot...

Page 26: ...2 EA TT 3500G 2 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise commingle parts from other systems...

Page 27: ...ed grade J 628338G 2 EA W 118614G 12 EA Z 3361G 12 EA EE 118615G 12 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not uti...

Page 28: ...EA W 118614G 12 EA Z 3361G 12 EA EE 118615G 12 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise co...

Page 29: ...G 12 EA Z 3361G 12 EA EE 118615G 12 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise commingle part...

Page 30: ...1 0 25 mm 0 mm above finished grade J 628338G 2 EA W 118614G 12 EA Z 3361G 12 EA EE 118615G 12 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or re...

Page 31: ...and hooked over the MATT CR Post 1 Top Q 33909G 1 EA CC 4902G 2 EA DD 3910G 2 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT...

Page 32: ...p W 118614G 8 EA Z 3361G 8 EA CC 4902G 8 EA EE 118615G 8 EA Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or oth...

Page 33: ...ications comply with MUTCD requirements or comply with state specifying agency requirements YY 105379B 1 EA OR ZZ 105380B 1 EA Use only Trinity Highway parts that are specified herein for the MATT for...

Page 34: ...EA Z 3361G 2 EA EE 118615G 2 EA 628342B from Step 13 Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairing the MATT Do not utilize or otherwise...

Page 35: ...d the MATT 10 Gauge Head Rails back evenly Z 3361G 4 EA EE 118615G 4 EA 628342B from Step 13 Use only Trinity Highway parts that are specified herein for the MATT for assembling maintaining or repairi...

Page 36: ...ered taut when it does not deflect more than 1 25 mm when pressure is applied by hand in an up or down direction Use only Trinity Highway parts that are specified herein for the MATT for assembling ma...

Page 37: ...l Plate using the upstream hole in the post p 24 12 Ensure all MATT Guardrails are installed 31 787 mm 1 0 25 mm 0 mm from finished grade pp various 13 Ensure all MATT 12 Gauge Transition Guardrails W...

Page 38: ...m components Check for vandalism Check for damage caused by adverse weather conditions i e erosion weight of snow UV Check that the anchor cable appears taut Walk Up Inspections Recommended Frequency...

Page 39: ...g Detail Detail derived from information contained in the AASHTO Roadside Design Guide 4 th Edition 2011 IMPORTANT Trinity Highway does not direct grading Proper site grading must be accomplished befo...

Page 40: ...derived from information contained in the AASHTO Roadside Design Guide 4 th Edition 2011 IMPORTANT Trinity Highway does not direct grading Proper site grading must be accomplished before assembly of t...

Page 41: ...TrinityHighway com February 2022 NOTES...

Page 42: ...TrinityHighway com February 2022 NOTES...

Page 43: ...TrinityHighway com February 2022 NOTES...

Page 44: ......

Reviews: