10.3.2
Excavation depth:
The excavation depth is determined by the inlet and outlet pipe, invert levels relative to the bottom of
the tank, and allowing for the minimum base thickness shown. Dimension details of the tank are shown
on the relevant drawing, supplied with the plant. Ground instability at formation level e.g. running sand
may necessitate over-excavation and stabilisation with hard core or blinding concrete.
NOTE: Check that the depth to the base slab is within the Service Specification requirements for the
tank.
Dry site
Wet site
Tank Size
Excavation Size
Tank A (m)
Excavation Size
Tank B (m)
UK6
2.6 x 2.14
N/A
UK8
3.1 x 2.14
N/A
UK10
3.6 x 2.14
N/A
UK12
4.1 x 2.14
N/A
UK18
5.1 x 2.14
N/A
UK24
6.1 x 2.14
N/A
UK30
7.1 x 2.14
N/A
UK36
3.1 x 2.14
6.1 x 2.14
UK42
4.1 x 2.14
6.1 x 2.14
UK50
4.1 x 2.14
7.1 x 2.14
Summary of Contents for NOVO EN6-50
Page 1: ...Technical Installation Manual Tricel Wastewater treatment systems TTM T106 Rev 06 Nov 13...
Page 11: ...11 Tricel Novo UK12 gravity plant Tricel Novo UK18 gravity plant...
Page 13: ...13 Tricel NovoUK42 gravity plant 2 tank plant...
Page 14: ...14 Tricel Novo UK50 gravity plant 2 tank plant Example of stepped installation...
Page 39: ...39...