Installation
RT-SVX33E-EN
19
Electric Heat Requirements
•
Verify that the power supply complies with the electric
heater specifications on the unit and heater nameplate.
•
Inspect the heater junction box and control panel;
tighten any loose connections.
•
Check electric heat circuits for continuity.
Condensate Drain Configuration
An evaporator condensate drain connection is provided
on each unit. Refer to
“Unit Dimensions,” p. 11
for the
appropriate drain location.
A condensate trap must be installed at the unit due to the
drain connection being on the “negative pressure” side of
the fan. Install the P-Trap using the guidelines in
Figure 15,
p. 19
.
A condensate drain line must be connected to the P-Trap.
Pitch the drain lines at least 1/2 inch for every 10 feet of
horizontal run to assure proper condensate flow. Do not
allow the horizontal run to sag causing a possible double-
trap condition which could result in condensate backup
due to “air lock”.
Filter Installation
Each unit ships with 2 inch filters installed. The quantity of
filters is determined by unit size. Access to the filters is
obtained by removing the indoor fan access panel. If
included, filters are removed by pulling the filter removal
tool.
Refer to the unit Service Facts (shipped with each unit) for
filter requirements.
Note:
Do not operate the unit without filters.
Electrical Requirements
Main Electrical Power Requirements
•
Verify that the power supply complies with the unit
nameplate specifications.
•
Inspect all control panel components; tighten any
loose connections.
•
Connect properly sized and protected power supply
wiring to a field-supplied/installed disconnect switch
and to the main power terminal block (HTB1) in the unit
control panel.
•
Install proper grounding wires to an earth ground.
Note:
All field-installed wiring must comply with NEC
and applicable local codes.
Low Voltage Wiring (AC & DC) Requirements
•
Install the zone thermostat, with or without switching
subbase.
•
Connect properly sized control wiring to the proper
termination points between the zone thermostat and
the unit control panel.
Field Installed Power Wiring
An overall dimensional layout for the standard field
installed wiring entrance into the unit is illustrated in the
Unit Dimensions
section. To insure that the unit’s supply
power wiring is properly sized and installed, follow the
guidelines outlined below.
Note:
All field installed wiring must conform to NEC
guidelines as well as State and Local codes.
Verify that the power supply available is compatible with
the unit’s nameplate ratings. The available supply power
must be within 10% of the rated voltage stamped on the
nameplate. Use only copper conductors to connect the
power supply to the unit.
Figure 15.
Condensate trap installation
WARNING
Proper Field Wiring and Grounding
Required!
All field wiring MUST be performed by qualified
personnel. Improperly installed and grounded field
wiring poses FIRE and ELECTROCUTION hazards. To
avoid these hazards, you MUST follow requirements for
field wiring installation and grounding as described in
NEC and your local/state electrical codes. Failure to
follow code could result in death or serious injury.
NOTICE:
Use Copper Conductors Only!
Unit terminals are not designed to accept other types of
conductors. Failure to use copper conductors could
result in equipment damage.