RLC-SVX023A
9
11
UNT-PRC002-GB
Sound power levels
Discharge
Measurement conditions:
Measurements taken in a room adjacent to the room containing the FWD, at the outlet of the rectangular duct (1.5 m
long) fixed to its discharge opening.
Fan
Power level in dB(A), per Hz frequency band
Overall power
Unit
speed
125
250
500
1000
2000
4000
8000
dB(A)
1
55
50
42
37
37
31
30
46
FWD 08
2
57
54
47
40
30
38
40
50
3
58
57
50
42
32
40
43
53
1
57
51
45
42
34
33
28
48
FWD 10
2
58
54
48
45
38
39
35
51
3
60
58
50
48
40
42
39
54
1
57
51
45
42
34
33
28
48
FWD 12
2
58
54
48
45
38
39
35
51
3
60
58
50
48
40
42
39
54
1
56
62
50
48
39
38
36
56
FWD 14
2
61
66
55
53
47
46
45
60
3
63
69
58
56
50
50
49
63
1
57
63
51
49
40
39
37
57
FWD 20
2
61
66
55
53
47
46
45
60
3
63
69
58
56
50
50
49
63
Intake
Measurement conditions:
Measurements taken at the horizontal air intake.
Fan
Power level in dB(A), per Hz frequency band
Overall power
Unit
speed
125
250
500
1000
2000
4000
8000
dB(A)
1
56
55
55
53
46
45
42
57
FWD 08
2
63
62
60
60
53
53
53
64
3
66
65
63
62
56
55
57
67
1
62
58
55
58
51
48
44
61
FWD 10
2
66
63
60
62
56
55
52
66
3
70
67
63
65
59
59
57
69
1
62
58
55
58
51
48
44
61
FWD 12
2
66
63
60
62
56
55
52
66
3
70
67
63
65
59
59
57
69
1
66
65
65
65
57
50
46
68
FWD 14
2
73
72
69
71
64
59
57
74
3
78
76
73
75
69
64
63
78
1
68
72
64
64
56
52
50
69
FWD 20
2
76
76
68
71
65
61
61
75
3
78
79
71
74
69
66
66
78
Installation overview and
requirements
Contractor responsibilities
A list of the contractor responsibilites typically associated
with the installation process is provided in Table 2.
• Locate and maintain the loose parts. Loose parts are
located in the control panel.
• Install the unit on a foundation with flat support surfaces,
level within 5 mm and of sufficient strength to support
concentrated loading. Place the manufacturer-supplied
isolation pad assemblies under the unit.
• Install the unit per the instructions outlined in the
“Mechanical Installation” section.
• Complete all water piping and electrical connections.
Note:
Field piping must be arranged and supported to
avoid stress on the equipment. It is strongly recommended
that the piping contractor provide at least 1m of clearance
between the pre-installation piping and the planned location
of the unit. This will allow for proper fit-up upon arrival
of the unit at the installation site. All necessary piping
adjustments can be made at that time
• Where specified, supply and install valves in the water
piping upstream and downstream of the evaporator and
condenser, to isolate the heat exchangers for maintenance
and to balance/trim the system.
• Supply and install flow switches or equivalent devices
in both the chilled water and condenser water piping.
Interlock each switch with the proper pump starter and
Tracer UC800, to ensure that the unit can only operate
when water flow is established.
• Supply and install taps for thermometers and pressure
gauges in the water piping, adjacent to the inlet and outlet
connections of both the evaporator and the condenser.
• Where specified, supply and install strainers ahead of all
pumps and automatic modulating valves.
• Supply and install refrigerant pressure relief piping from
the pressure relief to the atmosphere.
• Start the unit under supervision of a qualified service
technician.
• Where specified, supply and insulate the evaporator
and any other portion of the unit, as required, to prevent
sweating under normal operating conditions.
• For unit-mounted starters, cutouts are provided at the top
of the panel for line-side wiring.
• Supply and install the wire terminal lugs to the starter.
• Supply and install field wiring to the line-side lugs of the
starter.
Table 2 – Installation Responsibility
Requirement
Trane supplied
Trane installed
Trane supplied
Field installed
Customer supplied
Customer installed
Foundation
Meet foundation requirements
Rigging
Safety chains
Clevis connectors
Lifting beams
Isolation
Isolation pads
Other type of isolators
Electrical
- Circuit breakers or fusible
disconnects (Optional)
- Unit mounted starter
- Wye Delta starter or AFD
(Adaptive Frequency Drive)
- Flow switches (may be field
supplied)
- Harmonic filters (on request
according to customer electrical
network and equipment)
- Circuit breakers or fusible disconnect
- Electrical connections to unit mounted
starter (optional)
- Electrical connections to remote
mounted starter (optional)
- Wiring sizes per submittal and local
regulations
- Terminal lugs
- Ground connections
- BAS wiring (optional)
- Control voltage wiring
- Chilled water pump contactor and
wiring including interlock
- Option relays and wiring
Water piping
Flow switches (may be field
supplied)
- Taps for thermometers and gauges
- Thermometers
- Strainers (as required)
- Water flow pressure gauges
- Isolation and balancing valves in water
piping
- Vents and drain on waterbox valves
- Pressure relief valves for water side
Insulation
Insulation
Insulation
Water piping connection
components
- Grooved pipe
- Grooved pipe to flagged
connection (optional)
Caution on exposure to
refrigerant
Respect recommendation of IOM
addendum
Unit Description