Cassette Unit Installation
Drilling a hole in existing ceiling (horizontal)
1.
Drill a 880 x 880mm hole following the outline indicated on the mounting template.
•
The center of the hole must be placed in the same position corresponding to the body of the
air-conditioning unit.
•
Determine the lengths and outlets of connecting piping, drain piping, and wiring cables.
•
In order to balance the installation in the ceiling and also to avoid vibrations, install wedges
as may be deemed necessary.
2. Determine the position of the support rods following perforations for rods indicated on the
mounting template.
•
Drill four holes of 12mm dia. and 45-50mm in depth at the places indicated on the ceiling.
Insert expansible anchors.
•
Place the hollow side of the rods towards the expansible anchor. Determine the length of
installation rods based on the height of the ceiling. Cut away any remaining and
unnecessary extension. If ceiling height is taller, determine the length of installation rods
according to the space available for installation.
3. Apply equal torque to hex nuts on all four hanging rods to ensure the correct balance of the unit.
•
Place the drain pipe in the right direction to allow it to adjust to the movement of the water
level controller.
•
Center the unit in a manner that may ensure uniform spacing between the body of the unit
and the four sides of the ceiling. The lower side of the body of the unit must penetrate the
ceiling in approximately 10 to12 mm.
•
In general, the L distance represents half of the length of the installation rod.
•
Once the unit has been installed, apply final torque to all nuts.
Drilling a hole in a ceiling of new construction
1.
In the case of new construction, hanging rods may be inserted in advance (see point No. 2 in
section above). Rods must have the capacity to support the weight of the indoor unit and must
be unable to become loose due to the effects derived from concrete compression.
2. After installing the body of the unit, install the mounting template over the air conditioning unit
using M6 x 12 screws in order to determine in advance the sizes and positions of ceiling holes.
•
Before the installation, make sure the ceiling maintains proper leveling.
•
Refer to point No. 1.
3. See point No. 3 in section above
4. Remove the installation template.
Note: In order to install the body of the unit, adjust all four screws (M6 x 12) to the air
conditioning unit to ensure its grounding.
Summary of Contents for 2MCC05-C
Page 24: ...24 MS SVN056C EN Concealed Unit Installation Performance Curves...
Page 25: ...MS SVN056C EN 25 Concealed Unit Installation...
Page 71: ...MS SVN056C EN 71 Wiring Diagrams Outdoor Unit Cooling Only 4TTK05 D 36K 3 Phase...
Page 72: ...72 MS SVN056C EN Wiring Diagrams Outdoor Unit Cooling Only 4TTK05 D 48K 3 Phase...
Page 73: ...MS SVN056C EN 73 Wiring Diagrams Outdoor Unit Cooling Only 4TTK05 D 60K 3 Phase...
Page 74: ...74 MS SVN056C EN Wiring Diagrams Outdoor Unit Cooling Only Heat Pump 4TWK05 D 36K 3 Phase...
Page 75: ...MS SVN056C EN 75 Wiring Diagrams Outdoor Unit Cooling Only Heat Pump 4TWK05 D 48K 3 Phase...
Page 76: ...76 MS SVN056C EN Wiring Diagrams Outdoor Unit Cooling Only Heat Pump 4TWK05 D 60K 3 Phase...
Page 78: ......
Page 79: ......