Refrigeration Service Operations
128
3. Pressurize the refrigeration system and test for
leaks. If no leaks are found, evacuate the
system.
4. Recharge the unit with refrigerant and check
the compressor oil.
Pilot Solenoid
Removal
Non-Soldered Connections
1. Pump down the low side and equalize pressure
to slightly positive.
2. Disconnect the lines to the solenoid and
immediately cap to prevent moisture and air
from entering the system.
NOTE: The lines from the three-way valve to the
pilot solenoid will leak refrigerant at a high
velocity and should be capped.
3. Disconnect the electrical wires and remove the
pilot solenoid.
Soldered Connections
1. Recover the refrigerant
2. Disconnect the solenoid coil wires from the
main wire harness and remove the solenoid
coil from the solenoid valve.
3. Unsolder the lines from the solenoid valve and
remove from the unit.
Installation
Non-Soldered Connections
1. Replace the pilot solenoid in the unit.
2. Remove the caps from the lines and connect
lines to the pilot solenoid. Connect line from
the three-way valve first. Connect wires to the
valve.
3. Open the refrigeration valves and place the
unit in operation.
4. Check for leaks.
Soldered Connections
1. Clean the tubes for soldering.
2. Remove the solenoid coil from the solenoid
valve.
3. Place the valve in position and solder
connections.
4. Pressurize the refrigeration system and check
for leaks. If no leaks are found, evacuate the
system.
5. Recharge the unit with refrigerant.
Pressure Regulator Valve
Removal
1. Pump down the low side and equalize pressure
to slightly positive.
2. Release remaining pressure and unsolder
pressure regulator valve from the accumulator
tank and suction tube.
Installation
1. Clean the tubes for soldering.
2. Place the valve in position and solder
connections.
3. Pressurize the low side and check for leaks.
4. If no leaks are found, evacuate the low side.
5. Open the refrigeration valves, and place the
unit in operation. Check the refrigerant charge
and add refrigerant as required.
Receiver Tank
Removal
1. Remove the refrigerant charge.
2. Unsolder the inlet tube from the receiver tank.
3. Unsolder the filter drier line from the receiver
tank outlet tube.
4. Unbolt the mounting brackets and remove the
receiver tank from the unit.
Summary of Contents for 914970
Page 3: ...3...
Page 10: ...Table of Contents 10...
Page 40: ...Operating Instructions 40...
Page 82: ...Electronic Controls 82...
Page 92: ...Electrical Maintenance 92...
Page 124: ...Refrigeration Maintenance 124...
Page 140: ...Hilliard Clutch Maintenance 140...
Page 160: ...Refrigeration Diagrams 160...
Page 163: ...Index 163 W wiring 85 wiring diagrams 165...
Page 164: ...Index 164...
Page 166: ...Wiring and Schematic Diagrams Index 166...
Page 167: ...167 Cab Control RD Wiring Diagram...
Page 168: ...168 RD w o Thermostat Cab Control Schematic...
Page 169: ...169 RD Cab Box Wiring Diagram...
Page 170: ...170 RD Cab Control w Thermostat Schematic Diagram...
Page 171: ...171 RD 50 STD 3 Phase Wiring Diagram Page 1 of 2...
Page 172: ...172 RD 50 STD 3 Phase Wiring Diagram Page 2 of 2...
Page 173: ...173 RD 50 STD 3 Phase Schematic Diagram Page 1 of 2...
Page 174: ...174 RD 50 STD 3 Phase Schematic Diagram Page 2 of 2...
Page 175: ...175 RD 30 STD Wiring Diagram Page 1 of 2...
Page 176: ...176 RD 30 STD Wiring Diagram Page 2 of 2...
Page 177: ...177 RD 30 STD Schematic Diagram Page 1 of 2...
Page 178: ...178 RD 30 STD Schematic Diagram Page 2 of 2...
Page 179: ...179 RD 30 C S Wiring Diagram Page 1 of 2...
Page 180: ...180 RD 30 C S Wiring Diagram Page 2 of 2...
Page 181: ...181 RD w CYCLE SENTRY Schematic Diagram Page 1 of 2...
Page 182: ...182 RD w CYCLE SENTRY Schematic Diagram Page 2 of 2...
Page 183: ...183 RD 50 C S 3 Phase Wiring Diagram Page 1 of 2...
Page 184: ...184 RD 50 C S 3 Phase Wiring Diagram Page 2 of 2...
Page 185: ...185 RD w CYCLE SENTRY Schematic Diagram Page 1 of 2...
Page 186: ...186 RD w CYCLE SENTRY Schematic Diagram Page 2 of 2...