![Telemark TT-6 Instruction Manual Download Page 12](http://html1.mh-extra.com/html/telemark/tt-6/tt-6_instruction-manual_1081923012.webp)
T elemark TT-6 Power Supply
INSTALLATION
Introduction
Please see Figure 1-A, Main Cabinet
The TT Electron Beam Power Supply Main Cabinet and Sweep are designed to be
mounted in a standard 19 inch electronic instrument cabinet. Any suitable place
on a vacuum system that has a standard 19 inch wide opening may be used.
There should be minimum 6" (152mm) clearance at the back to allow proper air
flow. All modules must be secured in the cabinet before electrical connections are
made. The installation procedures are described below.
THE MAIN CABINET WEIGHS OVER 150 LBS.
IT MUST BE SET ON RAILS IN A 19" CABINET.
IT IS VERY HEAVY! HANDLE WITH CARE!
System Grounding Practice
See Figure 3-A and 3-B, Vacuum Tank Grounding Installation
A good ground is necessary to assure safe and proper operation of the power
supply. The following practices are recommended to assure a good ground.
NOTE - THE POWER SUPPLY MUST BE CONNECTED TO AN
ISOLATED EARTH GROUND AS SHOWN IN FIG. 3-A, 3-B or
3-C, FAILURE TO CONNECT THE POWER SUPPLY TO AN
ISOLATED EARTH GROUND COULD CAUSE SEVERE
DAMAGE TO THE POWER SUPPLY AND/OR
AUXILIARY ELECTRONIC CONTROL EQUIPMENT AND
WILL VOID THE WARRANTY.
INSTALLATION
3-1