Figure 5: Flow Fault Test
To perform a flow fault test:
1. Block probe tip inlet with finger for approximately 5 seconds.
2. If successful, the pump will flow fault and the display will flash SUCCESSFUL, as shown in
.
3. Select
NEXT
to switch the pump ON and continue warm-up cycle.
Figure 6: Successful Test
If the monitor fails the flow fault test, the screen shown in
remains
displayed.
3.5. Time and Date
The time and date are displayed as shown in
. Verify they are correct, as
they are used with datalogging.
Figure 7: Time and Date
3.6. Calibration Due
Calibration of the monitor is important.
By default, CAL DUE date is set to 365 days, but can be set to from 1 to 400 days.
The CAL DUE date is updated when the monitor is successfully calibrated.
Note: The monitor logs a successful Flow Fault test or if
SKIP