3.The processes is operated on a strict self-test, to prevent defective products into the next process.
4.When taking the mainboard,operator must do gently to avoid crashing or knocking the components.
Prepared
:
Bin Tang Checked by
:
Approved by
:
S.T Total:
PRECAUTIONS
1.The real goods used above items must be the same as BOM list's goods.
2.Operator should wear Gloves when operating.
gound point of source PCB board that it's delaying about 5 seconds as Fig.A.
When finishing the operation,plug LVDS wire between mainboard and source PCB board ,
then pull the cable of 11MΩ resistance out.
Set Oin Blower on the processing station before pluging LVDS wire as Fig.1 that it is placed
about 30 CM length and 45 degree angel between Oin Blower and worktable.
Take a cable with one resistance of 1MΩ to connect RF of mainboard and the copper
PROCESS DESCRIPTION
Oper.Parameter
Before pluging LVDS wire,it must be done to do EDS well,advoiding damage of borning
circuit.
Oin Blower
Name
Pair of Electrostatic Gloves
FIXTURES & INSTRUMENTS
Ass'y No.
H7-KD270NZG-UR0
Section
CTV ASSEMBLY
Part Number
Description
Specification
Model
40D2700B MS08BP-AP
NO.
10/23
Customer
Oper. Name
Do EDS before pluging LVDS wire
Remark
Electrostatic Mark
WORK INSTRUCTION
File No.
:
OS-C000390.00
Issue Date
:
2015/11/13
1.0
Modified Date
:
Fig.1
Images are only for reference :
When production ,prevail with
art materials , ODF information
and the real product of the
batch.
mainboard
Before pluging LVDS wire,it must be done to do
EDS well,advoiding damage of borning circuit
A
45 degree angel
30 CM length
connection to RF of
mainboard
connection to copper gound
point of source PCB board
resistance of
1M