Instrument Setup
A-96.250.341 / 061015
37
4.
Instrument Setup
After the analyzer is installed according to the previous instructions,
connect the power cord. Do not switch on power, yet!
4.1.
Establish sample flow
1
Open flow regulating valve,
see
Fluidics AMI Powercon Specific, p. 11
2
Wait until the flow cell has been completely filled.
3
Switch on power.
4
Adjust the sample flow to 5 - 10 l/h.
5
Let the instrument run-in for 1 h.
This recommendation is valid for rinsed cation exchanger
resin (nuclear grade) delivered by Swan.
Not rinsed cation exchanger resin from other suppliers, can
take a run-in period of several hours to several days.
4.2.
Programming
Sensor
parameters
Program all sensor parameters in Menu 5.1.2.1,
<Installation> <Sensors> <Sensor parameters>:
The sensor characteristics are printed on the label of each sensor.
Enter the:
Cell constant [cm
-1
]
Temperature correction [°C]
Cable length
Note:
Cable length [m] Set the cable length to 0.0 m if the
sensors are installed in the flow cell on the AMI monitor.
Temperature compensation: The default setting for sensor 1
(specific conductivity) is ammonia.
87-344.203
UP-Con1000SL
Sensor type
SW-xx-xx-xx
ZK = 0.0417
Cell constant
SWAN AG
DT = 0.06 °C
Temperature correction