Assembly Overview Notes
Generally there is no unique sequence for installation of the Premier VS system. A review of the job site will
often indicate a logical installation order. However, it is typical to start at the end of the branch with the furthest
Burner location and continue that Branch downstream towards the Vacuum Pump, then begin again with the
next Branch. Generally, 10 ft (3 m) increments of Tube and Reflector can be used until one reaches the
Common Tailpipe areas or Vacuum Pump connections. The general order of material in this manual is
recommended for low-hassle installation purposes.
The Installation of the Entire System potentially consists of 5 individual Parts, one Part for each major
component / system;
1-
Radiant Line System, (Heat Exchangers)
2-
Vacuum Pumps & Ventilation Systems,
3-
Optional Combustion Air Supply System,
4-
Gas Supply System, and
5-
Electrical System(s)
Directions for the installation of each component / system are therefore found in the respective sections
along with general information and safety notes as required