4.3 Unpacking
The SF-902S system is shipped partially assembled. Some parts are left off for protection during shipping.
Interconnect and sensor cables require installation prior to use.
1. Inspect the crates and boxes for external damage. Be sure to check underneath the crate for possible
forklift damage. Report any damage to the shipping company and SuperFlow Customer Service.
2. Remove all components and accessories from the crates or boxes.
3. Inspect all components for loose parts or any damage.
4. Open the rear panel of the operator’s console and inspect for loose parts or damage. Ensure that all
circuit cards are secure and cables are properly seated in their connectors.
5. Position the sensor box on a stable surface. Locate the sensor box door key. Carefully open the sensor
box door, and inspect the inside of the sensor box for any loose parts or visible damage. Ensure all
circuit cards are secure and cables are properly seated in their connectors.
HEAVY OBJECTS.
Use lifting aids and proper lifting
techniques.
!
WARNING
4.4 Engine Docking Cart
The engine cart comes fully assembled except for
the support posts and engine mounts.
1. Set the jack post cross-member in place toward
the rear (absorber end) of the cart.
2. Install the two engine mount posts, one on
each side, toward the front of the cart. Install
extension tubes into the posts.
Figure 4.3 Engine Docking Cart
4.0 Installation