FP12 Mundo - Installation and Operation Manual
61
4.
Every time the chimney passes through a ceiling or a wall, install the appropriate firestop. When you
reach the desired height, install the roof support (not illustrated). (Refer to instructions included with
the support).
5.
Then, put the roof flashing (D) in place and seal the joint between the roof and the flashing with roofing
pitch. For sloping roofs, place the flashing under the upper shingles and on top of the lower shingles.
Nail the flashing to the roof, using roofing nails.
6.
Place the storm collar (E) over the flashing, and tighten it with the bolt supplied. Finally, seal the joint
between the storm collar and the chimney, using silicone caulking.
7.
Install the chimney cap (G).
8.
When a ventilated roof flashing is installed, precautions are to be taken not to caulk or seal the
ventilating openings.
**
THE STRUCTURAL INTEGRITY OF THE
FLOOR, WALL, AND CEILING/ROOF
MUST BE MAINTAINED.
NOTE: THE FLOOR AND WALLS BELOW THE
ATTIC MUST BE INSULATED USING THE SAME
INSULATION.