Maintenance
Waukesha Cherry-Burrell
Page 40
95-03057
October 2005
Scheduled Maintenance
The following table is provided only as a guideline. It may be necessary to modify the schedule to conform to actual
in-plant requirements. All changes should be documented by plant personnel.
Table 5: Table of Scheduled Maintenance
Frequency
Component
Suggested Service
Weekly
Mutator Shaft
Bearing
Lubricate each fitting with a handgun, approximately three shots.
Use a suitable NLGI Grade-2 bearing grease. (Not required for Extra Heavy Duty
Votator II.)
Shaft
Assembly
Remove shaft assembly at least once a week. Always use the removal trough skid
to avoid bottom blades scoring the heat transfer tube. Replace the mechanical seal
shell O-rings.
Product Tube
Inspect the tube’s inner chrome surface to be sure it is smooth and bright. If rough
areas, marks or chrome plating deterioration exist, locate and correct the cause.
Replace the tube, if necessary.
Scraper Blades Examine scraper blades weekly, or after 40 operating hours. Based on amount of
wear, establish service frequency.
Maintain blades in good condition for longest machine life and best production
rates. Reserve a complete set of spare blades for routine replacement. Worn or
rough blades reduce heat transfer and can damage the heat transfer tube.
Jacket/
Accumulator
Purge gathered oil from accumulator section of accumulator jacket. If ammonia
charge is dumped from accumulator daily, oil is carried back with it.
Monthly
Inlet and
Outlet Fittings
Replace O-rings on inlet and outlet fittings monthly, or more frequently as needed.
Gearmotor
Check oil level and add as required.
Semi-
Annually
Refrigerant
Inspect for oil and/or contaminants.
Flange O-rings Replace O-rings at least every 12-18 months.
Summary of Contents for Waukesha Cherry-Burrell Votator II
Page 64: ...Parts Lists Waukesha Cherry Burrell Page 64 95 03057 October 2005 Single Mechanical Seal...
Page 66: ...Parts Lists Waukesha Cherry Burrell Page 66 95 03057 October 2005 Double Mechanical Seal...
Page 75: ...Waukesha Cherry Burrell Addendum October 2005 95 03057 Page75 Vertical Refrigeration System...
Page 76: ...Addendum Waukesha Cherry Burrell Page 76 95 03057 October 2005 Horizontal Frame Options...
Page 78: ...Addendum Waukesha Cherry Burrell Page 78 95 03057 October 2005 Vertical Hydraulic Schematic...
Page 83: ......