19
4. POST-INSTALLATION CHECKLIST
***
USE A SEPARATE INSTALLATION CHECKLIST FOR EACH POD
***
***
ADDITIONAL COPIES OF THIS CHECKLIST CAN BE FOUND AT:
http://www.sportsartamerica.com/saf/support/technicalsupport/technical_support3.asp
***
Inverter Serial Number :
After setting up a Green System Pod (one Inverter and less than or equal to ten Green System Cardio
Units) inspect the following:
ITEM 1:
Before checking anything else, first make sure that the electrical panel circuit breaker,
and Inverter power switch are turned off. If not, turn off power in those areas to prevent electrical
shock during the inspection.
ITEM 2:
Inspect the Inverter/Boost Converter connection. Make sure that the connectors are
inserted fully, that screws are in place, and that screws are tight. Double check that the power
cord is connected properly.
ITEM 3:
Make sure connectors between Green System fitness products are in place and
secured with screws. Collect and hide power cords into their raceway channels. All raceway
channels should be trimmed to fit, completely covering the cords.
Installation Procedures Overview
Post Installation Checklist