Strainer - Inspection and Replacement
(Fig. 19)
Strainers are installed on the unit. These strainers must be checked and cleaned periodically
(approximately every three (3) to six (6) months) to prevent the build up of any sediment.
∆
The combination of electricity, steam, and water can pose a very dangerous
situation. Turn off / disconnect all electric power before attempting any maintenance
procedures.
1. Follow the shutdown procedure to take the unit off-line before attempting to replace
the energy source strainer.
2. The exact location of the strainers can differ between units. Reference the drawing
supplied with the unit to identify the location of the strainers on the unit.
3. Carefully break the line connections on the inlet and outlet side of both strainers.
4. Remove and examine the strainers.
5. Remove any sediment that is present in the strainers. If they can not be satisfactorily
cleaned, replace with new strainers.
6. Place the strainers back in-line in the system.
7. Reconnect the inlet and outlet lines to each strainer.Follow recommendations contained
in the manufacturer’s documentation, local codes,or accepted contractor practices as
to the use and / or type of joint compound or sealer atthe connections.
8. Follow the startup procedures to put the unit back on-line. Carefully check all connections
for any sign of leakage.