Mounting the Unit
The unit should be mounted to the floor using the four individual footmounts supplied,
following applicable local code requirements, or accepted standards for the specific
installation site and for the unit purchased. In areas prone to seismic activity, it is
recommended that the unit be mounted to the floor, according to recommended procedures
for the site, to make the units less susceptible to seismic damage.
Preliminary Procedures
Spirax Sarco packaged Steam Generators are installed following this simple procedure:
1. Connect the feed water supply to the feed water inlet;
2. Connect the generated clean steam outlet to the clean steam outlet;
3. Connect the safety valve and discharge to a safe area;
4. Connect the primary supply (steam or high temperature water) to the unit;
5. Connect the condensate or return water line to the return pipework;
6. Connect the applicable power supply (if the unit is packaged with an electrically activated
pressure or control component);
7. Connect the appropriate instrument (control) air supply;
8. Connect the Drain / bottom blowdown connection to the correct system pipework;
Each unit is supplied with drawings that indicate the location and specifications for each
connection that must be made.
In addition, the drawings indicate the flow direction of both the steam and primary supply.
Connecting the Feed Water Source and Generated Clean Steam
Outlet
∆
Note: Before making any connections of feed water inlet or generated clean
steam outlet to the unit, assure that all pipework is clean and free of foreign material
or, scale. This can usually be accomplished by “blowing out” the pipe. Any foreign
material or scale entering the unit can adversely affect operation and performance.
∆
The drawings used in this manual are only examples. For the connections of
the ordered generator always refer to the drawings attached to the generator.
Feed Water Supply
The first step in the installation process is to connect the feed water supply to the feed
water inlet connection (Fig. 4).
The exact location for this specific unit, as well as pipe diameter, can be determined from
the drawings supplied with the unit.
A manual shutoff valve should be installed upstream on the feed water source as an
isolation device. The shutoff valve should be in the closed position and remain so until
the instalation is complete.
∆
Note: All pipework connections for clean steam and water should be flanged
or sanitary design, type of gasket material should be suitable for clean steam
application.