3.696.5275.210
16
Ancillary Service
Spirax Sarco recommends the installation of sample point throughout the system.
HTM 2031 also specifies that throughout the process of generation, system sample points
should be located at the followings points as a minimum.
These points will allow an easy sampling and testing system.
- Mains water
- Treated water (sample points between stages)
- Feed Water / Boiler water
- Steam generator water
- Steam at point of use
For further information contact Spirax Sarco.
Connecting the Primary Supply (Steam)
∆
Possible injury or death.
Assure that a manual shutoff valve is installed upstream in the steam line (energy source),
and that it is functioning properly. If any doubt exists concerning the integrity of the shutoff
valve, replace the valve before attempting installation. All primary supply valves should be
closed and remain closed throughout the installation process. Connect the primary supply
to the line(s) leading to the pressure control valve (Fig. 6).
The exact location of the pressure control valve for the specific unit, as well as primary
supply pipe diameter, can be determined from the drawing supplied with the unit.
Plant steam
Fig. 6
Summary of Contents for CSM-C