2-1 (E)
ZRD-1/ZRD-2/ZRCT-100/ZRCT-200
Section 2
Installation of Display Unit
2-1. Installation
Flow
Before starting the installation
.
Assemble all bases and install them. (Refer to Section 1-3-1.)
Fix the bases with the anchors.
.
Assemble all back frames. (Refer to Section 1-3-2.)
Fix the back frames with the anchors.
.
Set the number of display units and layout of the whole array in advance using the unit alignment tool.
For details on the setting procedure, refer to the document supplied with the unit alignment tool.
Install the first display unit in the system on the base.
Install the remaining eight display units that constitute the block of
nine units (3
)
3).
Connect the block of nine display units to the back frame.
Connect the display controller and cable to the display unit, then check
the operation.
Install the nine display units of the next block.
Connect the block of nine display units to the back frame.
Connect the display controller and cable to the display unit, then check
the operation.
Refer to Section 2-4-3.
Refer to Sections 2-4-4 and 2-4-5.
Refer to Section 2-5.
For the connection, refer to Section 5-1.
Refer to Sections 2-4-4 and 2-4-5.
Refer to Section 2-5.
For the connection, refer to Section 5-1.
For the connection, refer to Section 5-1.
For the fine adjustment in the Z direction,
refer to Section 2-6-1.
For the installation of protective material,
refer to Section 2-6-2.
Connect the display controller and cable to the display unit, then check
the operation of the whole array. Make the fine adjustment in the Z
direction as required.
Install the protective materials to the array.
Start
End