OPERATING MANUAL PAT-800/805 version 1.09
37
4.11 IEC lead test
Press
IEC TEST
. After that meter is prepared
for measurement.
When parameters must be changed press
SET
. Setting is performed as in section 4.2.
The following must be successively set:
LIMIT for R
PE
, measurement time R
PE
, LIMIT
for R
ISO
, measurement time R
ISO
.
Connect the mains plug into the test socket and the other into
the IEC socket.
Press
START
.
The measurement may be stopped before
the set time runs out by pressing
STOP/ESC
.
After measuring is completed, read the
result:
or
.