15K Pack HV Installation Manual
© 2020 Soluna Australia Pty Ltd
Page 15 of 25
Published date: November 2020
3.
Installation
The BS is too heavy for one person to carry. Ensure that two or more people are available
to do so.
Note
: an external bi-pole circuit breaker is required for battery output. During installation, an
external bi-pole DC isolator is required.
Space requirements during installation and operation
To ensure adequate ventilation during installation, where possible allow a space of 200 cm in
all directions around the BS.
Position
Minimum
spacing
(cm)
Remark
Side spacing
100
Allow clearance of at least 100 cm on either side of the BS.
Above
40
Nothing should be placed on top of the BS – allow clearance of at
least 40 cm.
Below
Always use the floor-mounting brackets supplied. Their height is
adjustable, allowing the installer to ensure that the BS is level when
installed (minimum height is the bottom of the bracket).
Backspacing
10
The BS needs to be installed against a wall.
Note
: for detailed requirements in relation to the width of the maintenance channel, escape
routes, etc., refer to applicable standards for the country/region in which the BS is to be
installed.