COMMISSIONING THE INVERTER
SOFAR 1100...3300TL-G3
59
6
Commissioning the inverter
6.1
Safety test before commissioning
ATTENTION
Check the voltage range
•
Ensure that the DC and AC voltages are within the permissible range
of the inverter.
6.2
Starting the inverter
1.
Switch on the DC switch.
2.
Switch on the AC circuit breaker.
When the DC output generated by the solar system is at a sufficient
level, the inverter starts automatically. A correct operation is indicated
by the screen displaying “normal”.
If the inverter displays an error message, consult chapter 8 for help.
NOTE
•
Different distribution network operators in various countries have
differing requirements for the grid connection of grid-coupled PV
inverters.
•
Ensure that you have selected the correct country code according
to regional authority requirements, and consult a qualified
electrician or employees of electrical safety authorities.
•
SOFARSOLAR is not responsible for the consequences of selecting
the incorrect country code.
•
The selected country code influences the device grid monitoring.
The inverter continuously checks the set limits and, if required,
disconnects the device from the grid.